Job filings
115-125 Franklin Street, Manhattan • Block 00177 • Lot 0013
13 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Sep 9, 2020 | 123838785 | Alteration Type II | PLAN EXAM - DISAPPROVED | LEGALIZATION OF TWELVE (12) HEAT AND TWO (2) LINEAR HEAT DETECTION FIRE ALARM SYSTEMS FOR DELUGE SPRINKLER SYSTEM IN ... | $10,000 | CONSOLIDATED EDISON OF N.Y |
| Jan 27, 2020 | 123838776 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | LEGALIZATION OF EXISTING AUTOMATIC SMOKE/HEAT DETECTION FIRE ALARM SYSTEM IN COMPLIANCE WITH FDNY LETTER DATED JANUAR... | $15,000 | CONSOLIDATED EDISON OF N.Y |
| Aug 8, 2019 | 123085375 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REPLACE DELUGE SYSTEM AROUND TRANSFORMER NUMBER 8 AT THE EXISTING CON EDISON LEONARD STREET SUBSTATION. THERE IS NO C... | $190,485 | CONSOLIDATED EDISON COMPANY |
| Jul 11, 2019 | 140687638 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF SECONDARY SPILL CONTAINMENT AT CON EDISON'S LEONARD STREET SUBSTATION. | $2,777,818 | CONSOLIDATED EDISON CO. OF NY |
| Jul 11, 2019 | 140727248 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF SECONDARY SPILL CONTAINMENT AT CON EDISON'S LEONARD STREET SUBSTATION TRANSFORMER #7. | $351,169 | CONSOLIDATED EDISON CO. OF NY |
| Jul 11, 2019 | 140597682 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | ALTER FOUNDATION AND MOAT TO ACCOMMODATE NEW REPLACEMENT TRANSFORMER #8 AT THE EXISTING CON EDISON LEONARD STREET SUB... | $369,902 | CONSOLIDATED EDISON COMPANY |
| Mar 28, 2019 | 121472432 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALL PROTECTIVE SYSTEMS TESTING (PST) TRAILER AT CON EDISON'S LEANOARD STREET SUBSTATION. THE TRAILER WILL BE MAIN... | $0 | CONSOLIDATED EDISON CO OF NY |
| Dec 6, 2017 | 140722243 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | INSTALLATION OF SECONDARY SPILL CONTAINMENT AT CON EDISON'S LEONARD STREET SUBSTATION TRANSFORMER #7. | $351,169 | CONSOLIDATED EDISON CO. OF NY |
| Nov 2, 2017 | 140712959 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | INSTALLATION OF SECONDARY SPILL CONTAINMENT AT CON EDISON'S LEONARD STREET SUBSTATION TR7. | $351,169 | CONSOLIDATED EDISON CO. OF NY |
| Aug 24, 2017 | 140686452 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | INSTALLATION OF SECONDARY SPILL CONTAINMENT AT CON EDISON'S LEONARD STREET SUBSTATION. | $2,777,818 | CONSOLIDATED EDISON CO. OF NY |
| Jan 18, 2017 | 140596004 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | ALTER FOUNDATION AND MOAT TO ACCOMMODATE NEW REPLACEMENT TRANSFORMER #8 AT THE EXISTING CON EDISON LEONARD STREET SUB... | $369,902 | CONSOLIDATED EDISON COMPANY |
| Nov 30, 2016 | 110340765 | Alteration Type II | SIGNED OFF | INSTALL NEW HVAC SYSTEM AT CON EDISON LEONARD ST SUBSTATION | $193,000 | CON EDISON CO |
| Jul 6, 2016 | 122640311 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | STORM HARDENING MODIFICATIONS AT CON EDISON'S LEONARD STREET SUBSTATION. WORK TO INCLUDE THE INSTALLATION OF FLOOD BA... | $104,075 | CONSOLIDATED EDISON CO. OF NY |