Issued Violation Status Severity Description Penalty Balance due Hearing
May 20, 2026 39554446M RESOLVE CLASS - 1 AT TIME OF MY INSPECTION DURING WEATHER ADVISORY SWEEP SITE MECHANICAL OPERATING EQUIPMENT ( BOOM LIFT ) WASN'T FULLY... $5,000 $5,000 Jul 30, 2026
May 20, 2026 39554448X RESOLVE CLASS - 2 AT THE TIME OF MY INSPECTION DURING WEATHER ADVISORY SWEEP OBSERVED MACHINE OPERATING EQUIPMENT ( BOOM LIFT ) WITHOUT... $625 $625 Jul 30, 2026
Feb 17, 2026 39550438Y RESOLVE CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXPIRED PERMIT. AT THE TIME OF INSPECTION OF A 5-STORY NEW BUILDING, A CONST... $1,280 $1,280 Mar 23, 2027
Jan 19, 2026 39549303Z RESOLVE CLASS - 1 ICY CONDITIONS OBSERVED ACTIVE SCAFFOLD PLATFORMS& ACCESS AREAS COVERED WITH SNOW& ICE.&ROOF LEVEL DUE TO INADEQUATE ... $2,500 $2,500 Oct 13, 2026
Jan 19, 2026 39549302R RESOLVE CLASS - 1 OBSERVED SUPPORTED SCAFFOLD ERECTED WITH MISSING SECTIONS, INCOMPLETE DECKING, AND ALTERED CONFIGURATION NOT IN ACCOR... $2,500 $2,500 Oct 13, 2026
Dec 1, 2025 35718008P RESOLVE CLASS - 2 FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQUIRED BY BC CHAPTER 33. AS NOTED AT TIME OF INSPECTION ON AN ACTIVE ... $3,125 $3,125 Jan 5, 2027
Aug 11, 2025 39543539H RESOLVE CLASS - 2 ALTERATION OF A 6 STORY BUILDING. OBSERVED ACTIVE CONSTRUCTION SITE WITH SUPPORTED SCAFFOLD @ EXP#1&2 WITH MAKESHIFT ... $3,125 $3,125 Oct 8, 2026
Jun 20, 2025 39541602M RESOLVE CLASS - 2 NOTE: AT TIME INSPECTION OF A 6-STORY BUILDING ONGOING CONSTRUCTION OPERATIONS, I OBSERVED A DEBRIS CHUTE IN PLACE AT... $2,500 $2,500 Mar 23, 2026
Jun 20, 2025 39541619Z RESOLVE CLASS - 1 NOTE: AT TIME INSPECTION OF A 6-STORY BUILDING ONGOING CONSTRUCTION OPERATIONS, I OBSERVED A GAS CAN INADEQUATELY BEI... $2,500 $2,500 Mar 23, 2026
Jun 20, 2025 39541617P RESOLVE CLASS - 1 NOTE: AT TIME INSPECTION OF A 6-STORY BUILDING ONGOING CONSTRUCTION OPERATIONS, I OBSERVED CONSTRUCTION MATERIALS AND... $5,000 $5,000 Mar 23, 2026
Jun 20, 2025 39541618R RESOLVE CLASS - 1 NOTE: AT TIME INSPECTION OF A 6-STORY BUILDING ONGOING CONSTRUCTION OPERATIONS, I OBSERVED CONSTRUCTION MATERIALS AND... $2,500 $2,500 Mar 23, 2026
Feb 10, 2025 39138007H RESOLVE CLASS - 1 FSWO ISSUED FOR WORK WITH OUT PERMIT. ATOI OBSERVED MAJOR DEMOLITION OF ALL 3 FLOORS. THE REMOVAL OF FIRE RATING DRYW... $5,030 $5,030 Aug 31, 2026