Job filings
224-228 Park Avenue South, Manhattan • Block 00847 • Lot 0040
155 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Dec 27, 2023 | 123774497 | Alteration Type I | SIGNED OFF | ALT-1 CHANGE OF USE ON FLOORS CEL,001,002,013 & PENTHOUSE FLOORS. CONSTRUCTION ON REAR YARD OF TV STUDIO, RECONST... | $8,200,000 | TF CORNERSTONE |
| Jun 28, 2023 | 140929547 | Alteration Type II | SIGNED OFF | STRUCTURAL WORK IN FLOORS CELLAR, 001, 002, 003 AS INDICATED ON PLANS FILED HEREWITH. NO CHANGE OF USE, EGRESS OF OCC... | $1,000,000 | 230 PARK AVENUE SOUTH |
| Apr 11, 2023 | 140959906 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2014 BUILDING CODES CHAPTER 33. ... | $0 | TF CORNERSTONE |
| Apr 7, 2023 | 123542318 | Alteration Type II | SIGNED OFF | REMOVAL OF AUTOMATIC SMOKE DETECTION SYSTEM FOR PRE-ACTION SPRINKLER SYSTEM | $5,000 | TF CORNERSTONE, INC. |
| Apr 7, 2023 | 123542309 | Alteration Type II | SIGNED OFF | REMOVAL OF AUTOMATIC SMOKE DETECTION SYSTEM FOR PRE-ACTION SPRINKLER SYSTEM | $5,000 | TF CORNERSTONE, INC. |
| Mar 28, 2023 | 123774488 | Alteration Type II | SIGNED OFF | HEREWITH FILING GENERAL CONSTRUCTION-INTERIOR CORE RENOVATIONS. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $4,860,690 | 230 PAS LLC C/O TF CORNERSTONE I |
| Mar 8, 2023 | 140991899 | Alteration Type II | SIGNED OFF | INTERIOR RENOVATION RELATED TO ELEVATOR WORK INCLUDING GENERAL CONSTRUCTION ON FLOORS CELLAR,001,002 & 003 AS IND... | $500,000 | 230 PARK AVENUE SOUTH |
| Sep 22, 2021 | 123378576 | Alteration Type II | SIGNED OFF | MECHANICAL AND PLUMBING MODIFICATIONS AS PER PLANS. | $434,500 | 230 PAS LLC C/O TF CORNERSTONE I |
| Aug 19, 2021 | 140876096 | Alteration Type III | SIGNED OFF | NORTH HOIST - INSTALLATION OF TEMPORARY CONSTRUCTION HOIST AS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2014 BUILDIN... | $0 | 230 PARK SOUTH, LLC |
| May 27, 2021 | 123739286 | Alteration Type II | SIGNED OFF | HEREWITH FILING GENERAL CONSTRUCTION IN THE 003 & 011 FLOORS AS INDICATED ON PLANS. NO CHANGE TO USE, EGRESS OR O... | $9,691,393 | TF CORNERSTONE |
| May 12, 2021 | 123739277 | Alteration Type II | SIGNED OFF | HEREWITH FILING GENERAL CONSTRUCTION IN THE 004,005 & 006 FLOORS AS INDICATED ON PLANS. NO CHANGE TO USE, EGRESS ... | $14,537,090 | TF CORNERSTONE |
| May 11, 2021 | 123739259 | Alteration Type II | SIGNED OFF | HEREWITH FILING GENERAL CONSTRUCTION IN THE 008,009 & 010 FLOORS AS INDICATED ON PLANS. NO CHANGE TO USE, EGRESS ... | $14,537,090 | TF CORNERSTONE |
| May 10, 2021 | 123739268 | Alteration Type II | SIGNED OFF | HEREWITH FILING GENERAL CONSTRUCTION IN THE 007 & 012 FLOORS AS INDICATED ON PLANS. NO CHANGE TO USE, EGRESS OR O... | $14,537,090 | TF CORNERSTONE |
| May 3, 2021 | 123498250 | Alteration Type II | SIGNED OFF | REPLACEMENT OF FCS FOR AN EXISTING APPROVED MODIFIED CLASS "E" FIRE ALARM SYSTEM AS PER BB 2015-025:2 (A) AND PLANS F... | $1,200 | 230 PAS LLC C/O TF CORNERSTONE I |
| Apr 1, 2021 | 123667754 | Alteration Type II | SIGNED OFF | MODIFICATIONS TO EXISTING FIRE ALARM SYSTEM INCLUDING RELOCATION OF DGP PANEL, ATS SWITCH AND NEW FDS/ATS CONNECTIONS... | $39,700 | 230 PAS LLC C/O TF CORNERSTONE |
| Nov 20, 2020 | 140975791 | Alteration Type III | PLAN EXAM - APPROVED | TENANT/OCCUPANT PROTECTION PLAN | $1,000 | TF CORNERSTONE |
| Nov 18, 2020 | 123370609 | Alteration Type II | SIGNED OFF | RENOVATION OF EXISTING BANK BRANCH FIRE ALARM SYSTEM INCLUDING RELOCATION OF FIRE ALARM STROBES. NO CHANGE IN USE, EG... | $13,696 | 230 PAS LLC |
| Nov 6, 2020 | 123674112 | Alteration Type II | SIGNED OFF | MODIFICATIONS TO EXISTING SPRINKLER SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $53,500 | 230 PAS LLC C/O TF CORNERSTONE |
| Oct 23, 2020 | 140848821 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY CONSTRUCTION HOIST AS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2014 BUILDING CODES CHAPTE... | $0 | 230 PARK SOUTH, LLC |
| Sep 29, 2020 | 123674121 | Alteration Type II | SIGNED OFF | INSTALLATION AND RELOCATION OF FIRE HOSE CABINETS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $18,500 | 230 PAS LLC C/O TF CORNERSTONE |
| Jul 28, 2020 | 123722882 | Alteration Type II | SIGNED OFF | TO DEMOLISH MASONRY TO CREATE OPENINGS IN CONJUNCTION WITH DOB JOB#123378576. BY PROVIDING TEMPORARY SHORING. THIS AP... | $63,000 | 230 PAS LLC |
| Mar 25, 2020 | 123774709 | Alteration Type II | SIGNED OFF | HEREWITH FILING GENERAL CONSTRUCTION & PARTIAL DEMOLITION OF SLAB IN THE 1ST FLOOR AS INDICATED ON PLANS. NO CHAN... | $86,500 | 230 PAS LLC C/O TF CORNERSTONE I |
| Mar 11, 2020 | 123734085 | Alteration Type II | SIGNED OFF | HEREWITH FILING SUBSEQUENT MECHANICAL & PLUMBING DEMO. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $60,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Feb 25, 2020 | 123757363 | Alteration Type II | SIGNED OFF | STRUCTURAL WORK FOR INSTALLATION OF NEW SWITCHGEAR VAULT AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCU... | $250,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Feb 4, 2020 | 123734076 | Alteration Type II | SIGNED OFF | HEREWITH FILING REMOVAL OF EXISTING SPRINKLER HEADS AND PIPING. INSTALLATION OF TEMPORARY SPRINKLER LOOP AS PER PLANS... | $27,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Feb 4, 2020 | 123871854 | Alteration Type II | SIGNED OFF | HEREWITH FILING REMOVAL OF EXISTING SPRINKLER HEADS AND PIPING. INSTALLATION OF TEMPORARY SPRINKLER LOOP AS PER PLANS... | $67,500 | 230 PAS LLC C/O TF CORNERSTONE I |
| Jan 17, 2020 | 123871630 | Alteration Type II | SIGNED OFF | HEREWITH FILING REMOVAL OF EXISTING SPRINKLER HEADS AND PIPING. INSTALLATION OF TEMPORARY SPRINKLER LOOP AS PER PLANS... | $67,500 | 230 PAS LLC C/O TF CORNERSTONE I |
| Jan 17, 2020 | 123734058 | Alteration Type II | SIGNED OFF | HEREWITH FILING REMOVAL OF EXISTING SPRINKLER HEADS AND PIPING. INSTALLATION OF TEMPORARY SPRINKLER LOOP AS PER PLANS... | $54,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Jan 10, 2020 | 123734067 | Alteration Type II | SIGNED OFF | HEREWITH FILING SUBSEQUENT MECHANICAL & PLUMBING DEMO. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $120,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Jan 10, 2020 | 123430037 | Alteration Type II | SIGNED OFF | HEREWITH FILING INTERIOR DEMO. DEMO OF ALL NON-LOAD BEARING PARTITIONS AND ALL TRADES. NO CHANGE TO USE, EGRESS OR OC... | $250,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Jan 10, 2020 | 123871845 | Alteration Type II | SIGNED OFF | HEREWITH FILING SUBSEQUENT MECHANICAL & PLUMBING DEMO. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $150,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Sep 11, 2019 | 123543932 | Alteration Type II | SIGNED OFF | MODERATE RENOVATION OF EXISTING BANK BRANCH INCLUDING NON-STRUCTURAL REMOVAL OF PARTITIONS AND RELATED FINISHES, AND ... | $188,635 | 230 PAS LLC |
| Jul 2, 2019 | 123776057 | Alteration Type II | PLAN EXAM - APPROVED | HEREWITH FILING SPRINKLER WORK IN CELLAR & 1ST FLOOR. NO CHANGE IN USE,EGRESS OR OCCUPANCY. | $10,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| May 24, 2019 | 123781700 | Alteration Type III | PLAN EXAM - APPROVED | PROFESSIONALLY CERTIFIED TENANT PROTECTION PLAN. | $1,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Mar 13, 2019 | 123378497 | Alteration Type II | SIGNED OFF | INSTALLATION OF ONE ADDITIONAL COOLING TOWER CELL, MOTORIZED VALVES TO BASE BUILDING AC UNITS, VFDS TO BASE BUILDING ... | $790,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Feb 20, 2019 | 123489607 | Alteration Type II | SIGNED OFF | MINOR SPRINKLER AND STANDPIPE MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $27,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Feb 4, 2019 | 123405449 | Alteration Type II | SIGNED OFF | MODIFICATIONS TO EXISTING SPRINKLER SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $30,000 | 230 PAS LLC C/O TF CORNERSTONE I |
| Jan 9, 2019 | 104332795 | Alteration Type II | SIGNED OFF | INTERIOR DEMOLITION OF NON LOAD BEARING DRYWALL PARTITIONS AND CEILINGS. INSTALLATION OF PARTITIONS AND CEILINGS AS S... | $120,000 | ROSE ASSOC INC - AS MGR PARK 230 |
| Jan 9, 2019 | 104680365 | Alteration Type II | SIGNED OFF | Propose to construct new entrance doors as shown on drawings filed herewith. No change in use, egress or occupancy. | $10,000 | Rose Associates, Inc. |
| Jan 9, 2019 | 120108891 | Alteration Type II | SIGNED OFF | PROPOSE TO INSTALL NEW PARTITIONS, CEILINGS & DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS... | $30,000 | ROSE ASSOCIATES INC |
| Jan 9, 2019 | 110117659 | Alteration Type II | SIGNED OFF | REMOVAL OF EXISTING DRY COOLER UNIT AND GLYCOL PUMP PACKAGE. EXISTING A / C EQUIPMENT CONNECTING WITH 3" CHILL WATER ... | $8,000 | ROSE ASSOCIATES |
| Jan 9, 2019 | 104711117 | Alteration Type II | SIGNED OFF | Filing herewith structural framing embracing for new mechanical unit as shown on drawings filed herewith. No change i... | $11,000 | Rose Associates, Inc. |
| Jan 9, 2019 | 104399492 | Alteration Type II | SIGNED OFF | PROPOSE TO DEMOLISH INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EG... | $80,000 | ROSE ASSOC INC - AS MGR PARK 230 |
| Jan 9, 2019 | 104364466 | Alteration Type II | SIGNED OFF | PROPOSE TO DEMOLISH EXISTING INTERIOR PARTITIONS, CEILINGS AND DOORS ON THE 11TH FLOOR AS SHOWN ON DRAWINGS FILED HER... | $10,000 | ROSE ASSOC INC - AS MGR PARK 230 |
| Dec 12, 2018 | 104729411 | Alteration Type II | SIGNED OFF | Installation of new individually coded Fire Alarm System on the 1st Floor Tenant space as indicated on drawings. No c... | $30,000 | Rose Associates, Inc. |
| Nov 27, 2018 | 120695523 | Alteration Type II | SIGNED OFF | ADDITIONS TO INDIVIDUALLY CODED FIRE ALARM SYSTEM ON THE 1ST FLOOR (CHASE) AS INDICATED ON DRAWINGS. | $5,000 | ROSE ASSOCIATES INC. |
| Sep 14, 2018 | 123540908 | Alteration Type II | PLAN EXAM - APPROVED | REMOVAL OF EXISTING PRE-ACTION VALVE AND CONNECTION OF EXISTING SPRINKLERS TO EXISTING FLOOR WET-PIPE SPRINKLER SYSTEM | $5,000 | TF CORNERSTONE, INC. |
| Sep 14, 2018 | 123540891 | Alteration Type II | PLAN EXAM - APPROVED | REMOVAL OF EXISTING PRE-ACTION VALVE AND CONNECTION OF EXISTING SPRINKLERS TO EXISTING FLOOR WET-PIPE SPRINKLER SYSTEM | $5,000 | TF CORNERSTONE, INC. |
| Jun 6, 2018 | 103988320 | Alteration Type II | SIGNED OFF | MODIFICATION TO EXISTING FIRE ALARM SYST EM AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $45,000 | BURSON-MARSTEKKER |
| May 9, 2018 | 103997294 | Alteration Type II | SIGNED OFF | MODIFICATION TO EXISTING SPRINKLER SYSTM AS PER PLANS FILED NO CHANGE IN USE SGRESS OR OCCUPANCY | $140,000 | BURSON -MARSTELLER |