1 West 57 Street, Manhattan • Block 01273 • Lot 0033
182 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Sep 4, 2025 | 121118968 | Alteration Type II | SIGNED OFF | MODIFY SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $9,000 | 754 LP C/O MILESTONE V. PARTNERS |
| May 3, 2024 | 121115113 | Alteration Type II | SIGNED OFF | MODIFICATION OF DUCTWORK AND DIFFUSERS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $18,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Mar 7, 2024 | 122427668 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REMOVE AND RELOCATE DIFFUSERS . INSTALL PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO ... | $10,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Feb 9, 2024 | 122440224 | Alteration Type II | SIGNED OFF | INSTALL 2 FIRE HOSE CABINETS . INSTALL SPRINKLER HEADS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS ... | $90,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Feb 7, 2024 | 120461963 | Alteration Type II | SIGNED OFF | PROPOSED ADDITONS AND MODIFICATIONS TO THE EXISTING CLASS C FIRE ALARM AND VOI CE COMMUNICATION SYSTEM. BASE BUILDING... | $5,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Feb 7, 2024 | 120943961 | Alteration Type II | SIGNED OFF | MODIFICATION FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $25,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Feb 7, 2024 | 122150493 | Alteration Type II | SIGNED OFF | ADDITIONS/MODIFICATIONS TO THE EXISTING CLASS "C" FIRE ALARM AND VOICE COMMUNICATION SYSTEM. THERE IS NO CHANGE TO US... | $31,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Feb 5, 2024 | 123175946 | Alteration Type II | SIGNED OFF | MODIFICATION OF EXISTING FIRE ALARM SYSTEM. | $5,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Feb 5, 2024 | 122404068 | Alteration Type II | SIGNED OFF | ADDITIONS, MODIFICATIONS TO THE EXISTING CLASS "C" FIRE ALARM AND VOICE COMMUNICATION SYSTEM. THERE IS NO CHANGE TO U... | $5,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Dec 20, 2023 | 121741400 | Alteration Type II | SIGNED OFF | DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE,... | $30,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Nov 9, 2023 | 123731701 | Alteration Type II | SIGNED OFF | NEW FIT-OUT AT EXISTING THIRD FLOOR RETAIL SPACE. WORK INCLUDES NON-LOAD BEARING PARTITIONS, FIXTURES, CEILING WORK, ... | $125,000 | BERGDORF GOODMAN |
| Nov 2, 2023 | 122425811 | Alteration Type II | SIGNED OFF | INSTALL NEW, REMOVE AND RELOCATE SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN... | $5,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Oct 3, 2023 | 123810616 | Alteration Type II | SIGNED OFF | INSTALLATION AND MODIFICATION OF SPRINKLER HEADS ALONG WITH RELATED PIPING. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $25,000 | C/O MADISON CAPITAL |
| Aug 29, 2023 | 122638967 | Alteration Type II | SIGNED OFF | DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE,... | $125,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Jul 19, 2023 | 123063406 | Alteration Type II | SIGNED OFF | ADDITIONS/MODIFICATION TO THE EXISTING CLASS "C" FIRE ALARM SYSTEM. THERE IS NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $50,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Jan 25, 2021 | 140948152 | Alteration Type II | SIGNED OFF | INTERIOR RENOVATION OF EXISTING 1ST FLOOR RETAIL SPACE. WORK INCLUDES NON-LOAD BEARING PARTITIONS, NEW DISPLAY FIXTUR... | $120,000 | BERGDORF GOODMAN |
| Oct 7, 2020 | 123477371 | Alteration Type II | SIGNED OFF | RELOCATE PLUMBING FIXTURE ALONG WITH RELATED PIPING. | $10,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Sep 18, 2020 | 123590569 | Alteration Type II | SIGNED OFF | MECHANICAL DUCT WORK. INSTALLATION OF PLUMBING FIXTURES ALONG WITH RELATED PIPING. | $45,000 | C/O MADISON CAPITAL |
| Oct 23, 2019 | 123590550 | Alteration Type II | SIGNED OFF | INTERIOR DEMOLITION, NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $10,000 | C/O MADISON CAPITAL |
| Oct 17, 2019 | 123253111 | Alteration Type II | SIGNED OFF | INSTALLATION , RELOCATE AND REMOVAL OF SPRINKLER HEADS WITH RELATED PIPING. | $20,000 | C/O MADISON CAPITAL |
| Oct 11, 2019 | 123811081 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | FILING HERE FOR MECHANICAL MODIFICATIONS. NO CHANGE OF USE OR EGRESS. | $30,000 | C/O MADISON CAPITAL |
| Dec 28, 2018 | 123104256 | Alteration Type II | SIGNED OFF | INSTALL NEW MECHANICAL DUCTWORK. INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH... | $30,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Dec 28, 2018 | 123104265 | Alteration Type II | SIGNED OFF | RELOCATE SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $10,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Dec 21, 2018 | 123400015 | Alteration Type II | SIGNED OFF | DEMO AND CONSTRUCTION OF PARTITIONS CEILINGS AND DOORS, NO CHANGE TO USE, OCCUPANCY OR EGRESS. | $153,000 | C/O MADISON CAPITAL |
| Dec 21, 2018 | 123401791 | Alteration Type II | SIGNED OFF | REMOVE AND RELOCATE SPRINKLER HEADS ALONG WITH RELATED PIPIN | $10,000 | C/O MADISON CAPITAL |
| Dec 18, 2018 | 123561109 | Alteration Type II | SIGNED OFF | ROOF REPLACEMENT OF EXISTING CHILLERS ON THE ROOF ABOVE THE 57TH STREET ELEVATOR MOTOR ROOM. NO ROOFING, FLASHING OR ... | $251,736 | SARA GOODMAN C/O MILESTONE V.ENT |
| Nov 15, 2018 | 122775513 | Alteration Type II | SIGNED OFF | CREATE CONNECTION ON 754 5TH AVE SIDE AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $30,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Aug 29, 2018 | 123533578 | Alteration Type II | PLAN EXAM - DISAPPROVED | PROPOSE MODIFICATION OF EXISTING CLASS C FIRE ALARM SYSTEM (INSTALL ONE NEW WALL MOUNTED STROBE LIGHT) AS PER PLANS F... | $3,500 | BERGDORF GOODMAN |
| Aug 13, 2018 | 123533587 | Alteration Type II | PLAN EXAM - APPROVED | PROPOSE TO ADD 1 SINK AND RELOCATE ONE SPRINKLER HEAD AND ADD MH DUCTWORK AS PER PLANS FILED HEREWITH. | $7,500 | BERGDORF GOODMAN |
| May 7, 2018 | 122775274 | Alteration Type II | SIGNED OFF | INSTALLATION OF SPRINKLER HEADS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $10,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Nov 20, 2017 | 121503015 | Alteration Type II | SIGNED OFF | INSTALL NEW MECHANICAL DUCTWORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $50,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Nov 1, 2017 | 122742960 | Alteration Type II | SIGNED OFF | DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE,... | $45,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Oct 10, 2017 | 122141306 | Alteration Type II | SIGNED OFF | INSTALL NEW STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $1,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Oct 3, 2017 | 122826399 | Alteration Type II | SIGNED OFF | INSTALL SPRINKLE HEADS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $5,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Sep 21, 2017 | 121503177 | Alteration Type II | SIGNED OFF | MODIFY SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $20,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Sep 13, 2017 | 122916817 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REPLACEMENT OF STEAM STATION . PLUMBING WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $400,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Aug 21, 2017 | 121465832 | Alteration Type II | SIGNED OFF | DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE,... | $180,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Aug 21, 2017 | 121465850 | Alteration Type II | SIGNED OFF | INSTALL NEW SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUP... | $20,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Aug 21, 2017 | 121527712 | Alteration Type II | SIGNED OFF | MODIFICATION TO THE CLASS C SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $5,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Jun 29, 2017 | 122950137 | Alteration Type II | SIGNED OFF | MODIFY SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $5,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Jun 29, 2017 | 122950146 | Alteration Type II | SIGNED OFF | MECHANICAL DUCT WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $10,000 | SARA GOODMAN C/O MILESTONE V.ENT |
| Jun 22, 2017 | 121764368 | Alteration Type II | SIGNED OFF | ADDITIONS AND MODIFICATIONS TO THE EXISTING CLASS "C" FIRE ALARM SYSTEM. THERE IS NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $90,000 | 754 LP C/O MILESTONE V. PARTNERS |
| May 23, 2017 | 122404077 | Alteration Type II | SIGNED OFF | REPLACEMENT OF EXISTING FIRE COMMAND STATION, AND UPGRADE OF EXISTING D.G.P.'S. THERE IS NO CHANGE TO USE, EGRESS OF ... | $75,000 | 754 LP C/O MILESTONE V. PARTNERS |
| May 8, 2017 | 122404059 | Alteration Type II | SIGNED OFF | ADDITIONS, MODIFICATIONS TO THE EXISTING FIRE ALARM AND VOICE COMMUNICATION SYSTEM. THERE IS NO CHANGE TO USE, EGRESS... | $75,000 | 754 LP C/O MILESTONE V. PARTNERS |
| May 4, 2017 | 122385114 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCC... | $15,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Mar 29, 2017 | 121516074 | Alteration Type II | SIGNED OFF | ADDITIONS/MODIFICATIONS TO THE EXISTING CLASS "C" FIRE ALARM AND VOICE COMMUNICATION SYSTEM. THERE IS NO CHANGE TO US... | $15,000 | 754 LP C/O MILESTON V. PARTNERS |
| Dec 28, 2016 | 122141324 | Alteration Type II | SIGNED OFF | RELOCATE 1 FIRE HOSE CABINET . INSTALL NEW SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO... | $370,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Nov 28, 2016 | 122239363 | Alteration Type II | SIGNED OFF | DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE,... | $300,000 | 754 LP C/O MILESTONE V. PARTNERS |
| Nov 21, 2016 | 122483561 | Alteration Type III | SIGNED OFF | INSTALLATION OF A PLYWOOD ENCLOSURE AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPA... | $0 | ALL SAFE LLC |
| Jun 10, 2016 | 122400687 | Alteration Type II | SIGNED OFF | DRY COOLER INSTALLATION AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $45,000 | 754 LP C/O MILESTONE V. PARTNERS |