Job filings
312 East 64 Street, Manhattan • Block 01438 • Lot 0010
24 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Dec 19, 2022 | 123838838 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | LEGALIZATION OF EXISTING AUTOMATIC SMOKE/HEAT DETECTION FIRE ALARM SYSTEM IN COMPLIANCE WITH FDNY LETTER DATED JANUAR... | $25,000 | CONSOLIDATED EDISON OF N.Y |
| Aug 10, 2022 | 123838874 | Alteration Type II | PLAN EXAM - DISAPPROVED | LEGALIZATION OF NINE (9) HEAT & ONE (1) LNEAR HEAT DETECTION FIRE ALARM SYSTEM FOR DELUGE SPRINKLER SYSTEM IN COM... | $10,000 | CONSOLIDATED EDISON OF N.Y |
| Jan 15, 2019 | 123384328 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | PERFORM CIVIL WORK NECESSARY TO SUPPORT THE SPILL PREVENTION CONTAINMENT & COUNTERMEASURE (SPCC) UPGRADES AT CON ... | $197,110 | CON EDISON COMPANY OF NEW YORK |
| May 24, 2018 | 122984878 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | PERFORM THE CIVIL WORK NECESSARY TO UPGRADE THE "SPILL PREVENTION CONTROL COUNTERMEASURES REQUIREMENTS AT CON ED'S E.... | $2,312,548 | CON EDISON COMPANY OF NEW YORK |
| May 24, 2018 | 140546531 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | PERFORM THE FOLLOWING CIVIL WORK FOR THE REPLACEMENT OF CON EDISON'S TRANSFORMER #4 AT THE EAST 63RD STREET SUBSTATIO... | $514,647 | CON EDISON COMPANY OF NEW YORK |
| Feb 2, 2018 | 122257379 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REPLACEMENT OF DELUGE SYSTEM FOR TRANSFORMER NO. 3 AT THE CON EDISON, EAST 63RD STREET SUBSTATION. THERE ARE NO CHANG... | $184,586 | CONSOLIDATED EDISON CO. OF NY |
| Mar 7, 2017 | 122714054 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF A DELUGE SYSTEM RELATED TO THE TRANSFORMER #4 REPLACEMENT AT CON EDISON'S EAST 63RD STREET SUBSTATION... | $180,836 | CON EDISON COMPANY OF NEW YORK |
| Jan 17, 2017 | 140586186 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PSF. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33... | $0 | JENCO CONTRACTING CORP |
| Sep 7, 2016 | 140545435 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | PERFORM THE FOLLOWING CIVIL WORK FOR THE REPLACEMENT OF CON EDISON'S TRANSFORMER #4 AT THE EAST 63RD STREET SUBSTATIO... | $514,647 | CON EDISON COMPANY OF NEW YORK |
| Sep 6, 2016 | 140545033 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | PERFORM THE FOLLOWING CIVIL WORK FOR THE REPLACEMENT OF CON EDISON'S TRANSFORMER #4 AT THE EAST 63RD STREET SUBSTATIO... | $514,647 | CON EDISON COMPANY OF NEW YORK |
| Mar 8, 2016 | 122697224 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | LEGALIZATION OF HEAT DETECTION SYSTEM FOR DELUGE SPRINKLER IN COMPLIANCE WITH FDNY LETTER DATED JANUARY 27TH, 2015 (F... | $10,000 | CONSOLIDATED EDISON CO. OF NY |
| Mar 8, 2016 | 122697215 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | LEGALIZATION OF EXISTING AUTOMATIC SMOKE DETECTION SYSTEM IN COMPLIANCE WITH FDNY LETTER DATED JANUARY 27TH 2015 (FPI... | $25,000 | CONSOLIDATED EDISON CO. OF NY |
| Jun 15, 2015 | 140336777 | Alteration Type III | SIGNED OFF | INSTALLATION OF SIDEWALK SHED AS SHOWN ON DRAWING. 2 SCAFFOLD FRAMES (H<40')WILL BE INSTALLED ON TOP OF THE SHED. ... | $0 | CONSOLIDATED EDISON CO. OF NY |
| May 6, 2015 | 140344090 | Alteration Type III | PLAN EXAM - IN PROCESS | CONED-INSTALLATION OF 8FT HIGH CONSTRUCTION FENCE AS SHOWN ON DRAWING. THERE WILL BE NO CHANGE IN USE, EGRESS OR OCCU... | $0 | CONSOLIDATED EDISON CO. OF NY |
| Apr 14, 2015 | 140333823 | Alteration Type III | PLAN EXAM - IN PROCESS | INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS SHOWN ON DRAWING. 2 SCAFFOLD FRAMES (H<40')WILL BE INSTALLED ON TOP OF... | $0 | CONSOLIDATED EDISON CO. OF NY |
| Apr 14, 2015 | 140334234 | Alteration Type III | PLAN EXAM - IN PROCESS | INSTALLATION OF SIDEWALK SHED AS SHOWN ON DRAWING. 2 SCAFFOLD FRAMES (H<40')WILL BE INSTALLED ON TOP OF THE SHED. ... | $0 | CONSOLIDATED EDISON CO. OF NY |
| Apr 7, 2015 | 140330773 | Alteration Type III | PLAN EXAM - IN PROCESS | INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS SHOWN ON DRAWING. 2 SCAFFOLD FRAMES (H<40')WILL BE INSTALLED ON TOP OF... | $0 | CONSOLIDATED EDISON CO. OF NY |
| Feb 11, 2015 | 140308076 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS SHOWN ON DRAWING. 2 SCAFFOLD FRAMES (H<40')WILL BE INSTALLED ON TOP OF... | $0 | METROPOLITAN ENTERPRISES INC |
| Dec 16, 2014 | 140292528 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | REPLACEMENT OF DELUGE SYSTEM FOR TRANSFORMER NO. 3 AT THE CON EDISON, EAST 63RD STREET SUBSTATION. THERE ARE NO CHANG... | $184,586 | CONSOLIDATED EDISON CO. OF NY |
| Nov 18, 2014 | 140239533 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | MODIFICATIONS TO THE CONCRETE PAD AND MOAT FOR TRANSFORMER 3 AT THE CON EDISON, EAST 63RD STREET SUBSTATION. THERE IS... | $153,092 | CONSOLIDATED EDISON CO. OF NY |
| Jul 16, 2014 | 122016638 | Alteration Type II | PLAN EXAM - DISAPPROVED | FILING FOR TEMPORARY WORK TRAILER REQUIRED TO SUPPORT WORK AT CON EDISON'S E 63RD ST SUBSTATION FACILITY. UPON APPROV... | $1,920 | CON EDISON CO OF NEW YORK, INC. |
| Apr 26, 2010 | 104673845 | Alteration Type II | SIGNED OFF | Installation of roof top A/C system including duct work and ventilation system at Con Edison's 63rd Street Substation... | $182,000 | Consolidated Edison Co. of NY |
| May 4, 2000 | 102851004 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REMOVE DELUGE PIPING AND HEADS FOR RE- PLACEMENT OF TRANSFORMER #5. REINSTALL PIPING AND HEADS AFTER NEW TRANSFORMER ... | $30,000 | CONSOLIDATED EDISON COMPANY |
| Apr 28, 2000 | 102642703 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | Modify existing concrete foundation for replacement of Transformer #5. There is no change of use, occupancy or egress... | $30,000 | Consolidat |