ECB violations
318 West 135 Street, Manhattan • Block 01959 • Lot 0054
15 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Aug 20, 2021 | 35583081X | RESOLVE | CLASS - 2 | PEDESTRIAN PAROTECTION DOES NOT MEET CODE SPECIFICATIONS.AT TIME OF INSPECTION AT 9 STORY BUILDING OBSERVED CONSRUCTI... | $2,400 | $0 | Nov 4, 2021 |
| Aug 20, 2021 | 35583080Y | RESOLVE | CLASS - 2 | BC3314.3.4.1 SCAFFOLDS SHALL BE INSTALED INSPECTED REPAIRED MAINTAINED ADJUSTED USED * REMOVED IN ACCORDANCE WITH SPE... | $0 | $0 | Nov 4, 2021 |
| Dec 24, 2020 | 35545628N | RESOLVE | CLASS - 1 | 3303.12-ELEVATOR NOT AT READINESS AT THE TIEM FO MY INSPECTION OF AN ACTIVE JOBSITE I OBSERVED THAT THE ELVATOR ONSIE... | $0 | $0 | Oct 21, 2021 |
| Oct 26, 2020 | 39031044R | RESOLVE | CLASS - 2 | THE INSTALLED WINDOWS FROM 2ND. TO 9TH. FLOOR WITH U-FACTOR: U-0.30 OR 0.31 CONTRARY TO U-0.18 INDICATED ON COMCHECK ... | $0 | $0 | Feb 10, 2021 |
| Oct 10, 2019 | 35449164Y | RESOLVE | CLASS - 1 | INADEQUATE TOE BOARDS.FAILURE TO ADEQUATELY INSTITUTE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARILY CONSTRUCTION.... | $5,000 | $0 | Oct 1, 2020 |
| Oct 10, 2019 | 35449165X | RESOLVE | CLASS - 2 | PEDESTRIAN PROTECTION.AT THE TIME OF INSPECTION I OBSERVD SIDEWALK SHED IN PLACE AT EXPOSURE 1,2,4 WITH PROJECTED SHA... | $2,400 | $0 | Oct 1, 2020 |
| Mar 19, 2019 | 35403389L | RESOLVE | CLASS - 1 | PERMIT HOLDER FAILED TO ENSURE EACH CONSTRUCTION OR DEMOLITION WORKER SUCCESSFULLY COMPLETED THE REQUIRED TRAINING UN... | $0 | $0 | Aug 8, 2019 |
| Mar 19, 2019 | 35403390Z | RESOLVE | CLASS - 1 | OWNER FAILED TO ENSURE EACH CONSTRUCTION OR DEMOLITION WORKERS SUCCESSFULLY COMPLETED THE REQUIRED TRAINING UNDE BC 3... | $0 | $0 | Aug 8, 2019 |
| Mar 19, 2019 | 35403391K | RESOLVE | CLASS - 1 | OWNER FAILED TO ENSURED EACH CONSTRUCTION OR DEMOLITION WORKER SUCCESSFULLY COMPLETED THE REQUIRED TRAINING UNDER BC ... | $0 | $0 | Aug 8, 2019 |
| Mar 19, 2019 | 35403392M | RESOLVE | CLASS - 1 | FAILURE TO HAVE A CONSTRUCTION SUPERINTENDENT PRESENT AT SITE AS REQUIRED. AT TIME OF INSPECTION ON AN ACTIVE JOBSITE... | $0 | $0 | Aug 8, 2019 |
| Mar 19, 2019 | 35403388J | RESOLVE | CLASS - 1 | PERMIT HOLDER FAILED TO ENSURE EACH CONSTRUCTION OR DEMOLITION WORKER SUCCESSFULLY COMPLETED THE REQUIRED TRAINING UN... | $0 | $0 | Aug 8, 2019 |
| Mar 19, 2019 | 35403394X | RESOLVE | CLASS - 2 | 3304.3.5 NOTIFICATION AND PERMIT REQUIREMENTS OF THE NEW YORK CITY TRANSIT AUTHORITY, THE METROPOLITAN TRANSPORTATION... | $1,250 | $0 | May 16, 2019 |
| Mar 19, 2019 | 35403395H | RESOLVE | CLASS - 2 | CONSTRUCTION SUPER DAILY LOGBOOK. AT TIME OF INSPECTION ON AN ACTIVE JOBSITE OF A 9STORY BUIDLING,CURRENTLY AT EXCAVA... | $2,500 | $0 | Aug 8, 2019 |
| Mar 19, 2019 | 35403386X | RESOLVE | CLASS - 1 | FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQURIED BY CHAPTER 33 (NO SITE SAFETY PLAN) AT TIME OF INSPECTION ON A... | $625 | $0 | Aug 8, 2019 |
| Mar 16, 2019 | 35403393Y | RESOLVE | CLASS - 2 | FAILURE TO MAINTAIN/DISPLAY ON-SITE DRAWINGS/DOCUMENTS REQUIRED BY CHAPTER 33 (NO DESIGN DRAWINGS FOR SHANTY). AT TIM... | $0 | $0 | May 16, 2019 |