| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| May 25, 2023 | 141022961 | Alteration Type II | PLAN EXAM - APPROVED | INSTALLATION OF SOLAR PV SYSTEM ON EXISITNG ROOFTOP. NO CHANGES TO THE EGRESS, USE OR OCCUPANCY. | $106,726 | GREATER HARLEM HOUSING DEVELOPME |
| May 11, 2021 | 123904061 | Subdivision Improved | COMPLETED | APPLICATION AND PLANS FILED HEREWITH TO COMBINE LOTS 58 & 56 NO WORK TO BE DONE_TENTATIVE LOT NUMBER 58 | $0 | GREATER HARLEM HOUSING DEV CORP |
| Oct 31, 2016 | 122771697 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | MODIFICATION TO EXISTING ANTENNA SITE, INSTALL RELATED RRH UNITS WITHIN EXISTING TELECOM ROOM IN THE BASEMENT. ALL WO... | $13,600 | AT&T MOBILITY |
| Sep 7, 2016 | 122481965 | Alteration Type II | SIGNED OFF | INSTALL (1) 5 TON HVAC UNIT IN EXISTING EQUIPMENT ROOM IN BASEMENT WITH RELATED CONDENSER ON ROOF. NO CHANGE TO EGRES... | $17,500 | GREATER HARLEM HOUSING CORP. |
| Nov 17, 2015 | 140326476 | Alteration Type III | SIGNED OFF | PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FILED FOR REMEDIAL REPAIRS AS PER PLANS. NO CHANGE IN USE OCCUPANCY... | $0 | HKS CONSTRUCTION CORP |
| Dec 27, 2012 | 120153984 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF NEW GAS BOILER, NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER TH IS APPLICATION | $75,800 | GHHDC |
| Apr 20, 2012 | 120530853 | Alteration Type III | SIGNED OFF | INSTALLATION OF ADDITIONAL EQUIPMENT IN EXISTING TELECOMMUNICATIONS ROOM IN TH E BASEMENT. INSTALLATION OF RELATED AN... | $25,000 | GREATER HARLEM HOUSING DEV. |
| Apr 24, 2002 | 103045759 | Alteration Type II | SIGNED OFF | INSTALL ADDITIONAL CABINETS IN EXISTING TELECOMMUNICATIONS ROOM IN BASEMENT. ANTENNAS ON ROOFTOP. NO CHANGE IN USE, O... | $15,000 | GREATER HARLEM HOUSING DEVEL COR |