| May 8, 2015 | 320833719 | Alteration Type III | SIGNED OFF | NON ILLUMINATED NON ADVERTISING ACCESSORY AWNING WITH DOWN LIGHTING | $3,961 | CRANE MANAGEMENT CORP |
| Mar 14, 2012 | 320155522 | Alteration Type I | SIGNED OFF | — | $100 | CRANE MANAGEMENT CORP. |
| Mar 9, 2012 | 320262363 | Alteration Type III | SIGNED OFF | CURB CUT | $0 | CRANE MANAGEMENT CORP. |
| Dec 10, 2010 | 310153909 | Alteration Type II | SIGNED OFF | INSTALLATION AN INTERIOR FIRE ALARM SYSTEM WITH A CENTRAL OFFICE CONNECTION AS PER PLANS FILED HEREWITH. FILED IN CON... | $50,000 | BKLYLN DIALYSIS CENTER, LLC |
| Feb 3, 2010 | 302173706 | Alteration Type I | SIGNED OFF | NEW CO. CHANGE TO USE GROUP 6 (PROFESS-IONAL OFFICES) AND USE GROUP 16 (WAREHOUSE). ALTERATION OF EXISTINGPLUMBING SY... | $1,403,071 | Brooklyn Dialysis Center LLC |
| Nov 30, 2009 | 320053936 | Alteration Type II | SIGNED OFF | IT IS PROPOSED TO INSTALL A NEW BOILER AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY. PLEASE NOTE ALL PLUM... | $10,000 | BROOKLYN DIALYSIS CENTER LLC |
| Mar 24, 2009 | 310075744 | Alteration Type II | SIGNED OFF | Modify sprinkler system in the building. (2) existing sprinkler heads to be removed, (2) existing sprinkler heads to ... | $30,000 | Brooklyn Dialysis Center LLC |
| Feb 14, 2006 | 301152650 | New Building | SIGNED OFF | NEW PLUMBING SEWER,2 WATER MAINS AS PER PLANS FILES HEREWITH. | $0 | CRANE MNAGEMENT CORP |
| Feb 8, 2006 | 301219438 | Alteration Type II | SIGNED OFF | NEW SPRINKLER SYSTEM FILED IN CONJUCTION WITH NEW BUILDING APPLICATION | $11,000 | CRANE MANAGEMENT CORP |
| Jan 24, 2006 | 301220952 | Alteration Type III | SIGNED OFF | BNP 01-251 104 FT FRONTAGE,BPP FILINGNB 301152650 | $0 | VICE PRESIDNET |
| Aug 13, 2002 | 301229418 | Alteration Type III | SIGNED OFF | TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH NEW BUILDING APPL.# 301152650. | $0 | CRANE MANAGEMENT |
| Oct 2, 2001 | 301111204 | Alteration Type I | PLAN EXAM - DISAPPROVED | NEW 2 STY STEEL FRAME WITH EXTERIOR MASO NRY WALLS BUILDINGS, WITH DR L INTERIOR PARTITIONS AS PER PLANS FILED HEREWITH | $290,000 | CRANE MANAGEMENT CORP |