77 Woodbine Street, Brooklyn • Block 03349 • Lot 0038
29 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Jul 21, 2025 | 39542661R | ACTIVE | CLASS - 2 | UPON REQUEST @ THE TIME OF INSPECTION GC FAILED TO PROVIDE/ MAINTAIN DOCUMENTS : NEIGHBOR'S AGREEMENT, SIDEWALK SHED ... | $6,250 | $6,250 | Sep 25, 2026 |
| Jul 21, 2025 | 39542662Z | ACTIVE | CLASS - 1 | OBSERVED ACTIVE SITE WITH INADEQUATE HOUSEKEEPING IN MULTI LOCATIONS @ EXP.1 ENTRANCE, EXP. 3 REAR YARD. BC 3303.4 & ... | $12,500 | $12,500 | Oct 1, 2025 |
| Jul 21, 2025 | 39542651N | RESOLVE | CLASS - 2 | OBSERVED ACTIVE SITE WITH MULTI VIOLATION CONDITIONS: CS FAILED TO CORRECT/MAINTAIN UNSAFE CONDITIONS, NO GUARDRAIL @... | $5,000 | $5,000 | Apr 19, 2027 |
| Jul 21, 2025 | 39542626L | ACTIVE | CLASS - 1 | OBSERVED ACTIVE SITE WITH MISSING GUARDRAIL SYSTEM @EXP. 1&3 BALCONY LEVELS ,NO SAFETY PRECAUTIONS IN PLACE UNDER CHA... | $25,000 | $25,000 | Sep 25, 2026 |
| Jul 21, 2025 | 39542627N | ACTIVE | CLASS - 1 | OBSERVED ACTIVE WORK SITE , GS FAILED TO PROVIDE OVERHEAD PROTECTION FOR ADJACENT PROPERTY@ EXP. 2. WORK WAS CONTRARY... | $12,500 | $12,500 | Sep 25, 2026 |
| Jun 10, 2025 | 39150567H | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION OF 5 STORY NEW BUILDING, TEMPORARY CONSTRUCTION FENCE NOT MAINTAINED NOR ERECTED AT REAR OF EXP... | $1,000 | $0 | Aug 20, 2025 |
| Jun 10, 2025 | 39150566X | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION OBSERVED TEMPORARY CONSTRUCTION FENCE ERECTED ATEXPOSURE # 1, REAR OR 2 AND 3. UPON REVIEW DEPA... | $0 | -$1,250 | Aug 20, 2025 |
| Mar 5, 2025 | 39537654M | RESOLVE | CLASS - 2 | EXP3 VERT MEMBERS AT STAIRCASE LOCATION SUPPORTING BASE OF SCAFFOLD FRAMES.PE DRAWINGS INDICATE 6 FOOT WALKTHROUGH FR... | $625 | $0 | Jun 16, 2025 |
| Mar 5, 2025 | 39537656X | RESOLVE | CLASS - 1 | FAILURE INSTITUTE SAFETY MEASURE.EXP3 OBSERVED STAIRCASE LEADING TO BASEMENT WITH TOP OF FOUNDATION WALL MISSING GUAR... | $12,500 | $12,500 | Jun 18, 2026 |
| Mar 5, 2025 | 39537655Y | RESOLVE | CLASS - 2 | EXP1 AT 3 AND 4 STORY SCAFFOLD MISSING GUARDRAIL AND BALCONIES MISSING GUARDRAILS,CREATING FALL HAZARD CONDITION FOR ... | $2,500 | $0 | Jun 16, 2025 |
| Oct 4, 2024 | 39533127M | RESOLVE | CLASS - 2 | SUPPORTED SCAFFOLD INSIDE THE ELEVATOR SHAFT DOES NOT SHOWN ON THE APPROVED SCAFFOLD DRAWINGSTOP ALL WORK AND USE OF ... | $0 | $0 | Dec 11, 2024 |
| Oct 4, 2024 | 39533126K | RESOLVE | CLASS - 2 | OBSERVED CONSTRUCTION FENCE INSTALLED AT REAR YARD EXP# 3 NO ADEQUATELY MAINTAINED, PLYWOOD PANEL NOT 8FT., AND DISLO... | $1,000 | $0 | Jul 14, 2025 |
| May 16, 2024 | 39528655J | RESOLVE | CLASS - 1 | 3309.10 PROTECTION OF ROOFS. RESPONDING A COMPLAINT OBSERVED: STEEL COLUMNS ERECTED AT 3RD FLOOR LEVEL ABOUT 16 FEET ... | $5,000 | $5,000 | Dec 3, 2024 |
| Mar 1, 2024 | 39526030K | ACTIVE | CLASS - 2 | FAILURE TO PROVIDE PROTECTION OF ADJOINING PROPERTY DURING CONSTRUCTION OR DEMOLITION AS REQUIRED- NO WINDOW PROTECTI... | $12,500 | $12,500 | Nov 18, 2024 |
| Mar 1, 2024 | 39526029N | ACTIVE | CLASS - 1 | A PROPOSED 5 STORY NEW BUILDING UNDER PERMIT B00529365. OBSERVED STEEL BEAMS CONNECTIONS CONTRARY TO APPROVE DRAWINGS... | $12,500 | $12,500 | Nov 18, 2024 |
| Nov 24, 2023 | 39523625X | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION I OBSERVED A SIDEWALK SHED ERECTED AT THE PLACE OF OCCURRENCE WITH WITHOUT A PERMIT. AN ACTIVE ... | $625 | $625 | Jun 11, 2024 |
| Aug 29, 2023 | 39521102H | RESOLVE | CLASS - 2 | RESPONDENT FAILED TO COMPLY WITH THE COMMISSIONER'S ORDER TO CORRECT THE VIOLATING CONDITION AND FILE A CERTIFICATE O... | $1,250 | $1,250 | Aug 1, 2024 |
| Aug 29, 2023 | 39521103J | RESOLVE | CLASS - 2 | RESPONDENT FAILED TO COMPLY WITH THE COMMISSIONER'S ORDER TO CORRECT THE VIOLATING CONDITION AND FILE A CERTIFICATE O... | $1,250 | $1,250 | Aug 1, 2024 |
| Jul 3, 2023 | 39518691H | RESOLVE | CLASS - 2 | ACTIVE CONSTRUCTION SITE.SUPERINTENDENT NOT ON SITE.FOLLOWING VIOLATING CONDITIONS OBSERVED:WORKERS NOT WEARING HARD ... | $0 | $0 | Feb 2, 2024 |
| Jul 3, 2023 | 39518674X | RESOLVE | CLASS - 1 | FAILURE TO INSTITUTE AND MAINTAIN SAFETY MEASURES.I OBSERVED ACTIVE CONSTRUCTION SITE .5 WORKERS ON SITE.WORKERS DOES... | $2,500 | $2,500 | Mar 28, 2024 |
| Jul 3, 2023 | 39518676J | ACTIVE | CLASS - 1 | ACTIVE CONSTR. SITE.5 WORKERS PRESENT.UPON REQUEST COMPETENT PERSON ALEXIS GOMEZ FOR PRE-SHIFT SAFETY MEETING,NONE WA... | $5,000 | $5,000 | Mar 28, 2024 |
| Jul 3, 2023 | 39518677L | RESOLVE | CLASS - 2 | ACTIVE CONSTRUCTION SITE.PROPOSED 5 STORY NB AT EXCAVATION/FOUNDATION PHASE.I OBSERVED LARGE AMOUNT OF DEBRIS ALL OVE... | $625 | $625 | Mar 28, 2024 |
| Jul 3, 2023 | 39518675H | RESOLVE | CLASS - 2 | ACTIVE CONSTRUCTION SITE.5 WORKERS PRESENT.UPON REQUEST COMPETENT PERSON ALEXIS GOMEZ FOR APPROVED S.O.E PLANS TO VER... | $0 | $0 | Mar 28, 2024 |
| May 22, 2023 | 39516907Z | RESOLVE | CLASS - 2 | UNSAFE CONDITIONS AND EQUIPMENT. OBSERVED SITE AT EXCAVATION PHASE AND SOIL IS STORED APPROX. 5FT HIGH ADJACENT TO TH... | $0 | $0 | Jul 26, 2023 |
| Apr 6, 2023 | 39515030R | RESOLVE | CLASS - 1 | AT THE TIME OF INSPECTION WHILE RESPONDING TO A COMPLAINT, I OBSERVED PARTIAL FOUNDATION IN PLACE AND EXCAVATION WORK... | $2,500 | $2,500 | Jun 14, 2023 |
| Apr 6, 2023 | 39515035X | RESOLVE | CLASS - 1 | AT TIME OF INSPECTION OBSERVED ELECTRICAL POWER IS IN USE AT THIS CONSTRUCTION SITE BY THE LOOSE CABLE FROM ADJACENT ... | $0 | $0 | Mar 5, 2024 |
| Apr 6, 2023 | 39515032K | RESOLVE | CLASS - 2 | AT THE TIME OF INSPECTION I OBSERVED UNAUTHORIZE / UNSPECIFIED VARIOUS BUSINESS SIGNS POSTED ON FENCE AT EXPOSURE #1,... | $0 | $0 | Jun 14, 2023 |
| Feb 7, 2023 | 39512782X | RESOLVE | CLASS - 1 | INSPECTION OF AN 5 STORY BUILDING WITH WORK IN PROGRESS, OBSERVED CONSTUCTION HAVE INSTALL PILES AND SHORE AT EXPOSUR... | $2,500 | $2,500 | Apr 15, 2024 |