| Apr 25, 2026 | 39553485K | RESOLVE | CLASS - 2 | BC 3303.3. AT THE TIME OF INSPECTION OF 11-STORY BUILDING OF APPROXIMATELY 6588 SQUARE FEET. UPON SHOUTING, WALKING T... | $2,500 | $2,500 | Feb 9, 2027 |
| Apr 25, 2026 | 39553487Y | RESOLVE | CLASS - 2 | BC 3303.4.2 (4). AT THE TIME OF MY INSPECTION OF 11-STORY NEW BUILDING, I OBSERVED DUMPSTER CONTAINER HOLDING DEBRIS ... | $2,500 | $2,500 | Feb 9, 2027 |
| Apr 25, 2026 | 39553486M | ACTIVE | CLASS - 2 | BC-3314.8.2. AT THE TIME OF MY INSPECTION OF 11-STORY NEW BUILDING, I OBSERVED THE PIPE SCAFFOLD IN PLACE AT EXPOSURE... | $2,500 | $2,500 | Feb 9, 2027 |
| Jan 5, 2026 | 39548771P | RESOLVE | CLASS - 1 | 28-405.1. AT TIME OF INSPECTION ON AN ACTIVE JOBSITE, I OBSERVED AT EXPOSURE #4 A KNUCKLE BOOM CRANE TRUCK LIFT ON TH... | $2,500 | $2,500 | Oct 19, 2026 |
| Jan 3, 2026 | 39548754N | RESOLVE | CLASS - 2 | BC 3303.3 AT THE TIME OF INSPECTION OF 11 STORY NEW BUILDING APPROXIMATELY 6588 SQUARE FEET, I OBSERVED NO CONSTRUCTI... | $2,500 | $2,500 | Oct 5, 2026 |
| Jan 3, 2026 | 39548673L | RESOLVE | CLASS - 2 | BC 3303.3. AT THE TIME OF MY INSPECTION OF 11 STORY NEW BUILDING APPROXIMATELY 6588 SQUARE FEET, I OBSERVED NO CONSTR... | $0 | $0 | Mar 11, 2026 |
| Dec 29, 2025 | 39548573Y | RESOLVE | CLASS - 2 | BC3303.3 WATCHPERSON 11 STORY NEW BUILDING, BUILDING APPROXIMATELY 6588 SQUARE FEET. SITE CLOSED CHAINED GATE PADLOCK... | $2,500 | $2,500 | Oct 20, 2026 |
| Oct 29, 2025 | 39546481H | RESOLVE | CLASS - 1 | AT THE TIME OF MY INSPECTION OF A 11 STORY BUILDING APPROXIMATELY 12,700 SQ. FT. I OBSERVED NO CONSTRUCTION ACTIVITIE... | $5,000 | $5,000 | Sep 22, 2026 |
| Sep 15, 2025 | 39544894R | RESOLVE | CLASS - 1 | AT THE TIME OF MY INSPECTION I OBSERVED AIR PRESSURIZED ALARM SYSTEM INSTALL ON SITE AT FIRST FLOOR LEVEL FOR STANDPI... | $0 | $0 | Aug 7, 2026 |
| Sep 15, 2025 | 39544895Z | RESOLVE | CLASS - 2 | BC3308.6.1.4 ALTERNATIVE SYSTEMS. AT TIME OF MY INSPECTION I OBSERVED CONCRETE POURING OPERATION IN PROGRESS AT 11TH ... | $2,500 | $2,500 | Aug 7, 2026 |
| Sep 13, 2025 | 39544851R | RESOLVE | CLASS - 2 | BC 3303.3 AT THE TIME OF MY INSPECTION 11 STORY NB BUILDING APPROXIMATELY 6588 SQUARE FEET. SITE CLOSED WATCHPERSONS ... | $2,500 | $2,500 | Aug 7, 2026 |