| Jan 17, 2020 | 340518103 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REPLACEMENT OF 2 GAS FIRED BOILERS AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILERS. THERE WILL BE NO CHANGE IN U... | $27,200 | CAPITAL ONE BANK |
| Jan 17, 2020 | 340518112 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REPLACEMENT OF GAS FIRED BOILER AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILER. THERE WILL BE NO CHANGE IN USE E... | $15,460 | CAPITAL ONE BANK |
| Dec 2, 2019 | 340673373 | Alteration Type II | SIGNED OFF | APPLICATION FILED TO MODIFY EXISTING ATM AREA AND ADD ADDITIONAL ATM MACHINE ALL AS PER PLANS FILED HEREWITH. NO CHAN... | $33,000 | CAPITAL ONE |
| Nov 14, 2019 | 340679643 | Alteration Type II | SIGNED OFF | THIS APPLICATION IS FILED FOR ONLY MECHANICAL HVAC UNIT SUPPLYING THE ATM VESTIBULE ONLY. NO CHANGE TO USE EGRESS OR ... | $15,750 | CAPITAL ONE |
| Sep 7, 2017 | 321055433 | Alteration Type II | SIGNED OFF | INTERIOR RENOVATION TO INCLUDE CONSTRUCTION OF NEW PARTITIONS AND FINISHES AS SHOWN ON PLANS. NO CHANGE IN USE, EGRES... | $5,000 | CAPITAL ONE |
| Apr 19, 2017 | 340494968 | Alteration Type II | PLAN EXAM - IN PROCESS | REPLACEMENT OF GAS FIRED BOILER AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILER. THERE WILL BE NO CHANGE IN USE E... | $15,460 | CAPITAL ONE BANK |
| Apr 19, 2017 | 340495039 | Alteration Type II | PLAN EXAM - IN PROCESS | REPLACEMENT OF GAS FIRED BOILERS AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILERS. THERE WILL BE NO CHANGE IN USE... | $27,200 | CAPITAL ONE BANK |
| Apr 11, 2017 | 340476078 | Alteration Type II | SIGNED OFF | REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY | $150,500 | CAPITAL ONE BANK |
| Feb 24, 2017 | 340476069 | Alteration Type II | PLAN EXAM - IN PROCESS | REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY | $150,500 | CAPITAL ONE BANK |
| Dec 27, 2016 | 340458472 | Alteration Type II | PLAN EXAM - IN PROCESS | REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY | $150,500 | CAPITAL ONE BANK |
| Apr 27, 2016 | 340376578 | Alteration Type II | PLAN EXAM - IN PROCESS | REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY | $150,500 | CAPITAL ONE BANK |