Latest action Job Type Status Work Cost Owner
Jan 17, 2020 340518103 Alteration Type II PERMIT ISSUED - ENTIRE JOB/WORK REPLACEMENT OF 2 GAS FIRED BOILERS AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILERS. THERE WILL BE NO CHANGE IN U... $27,200 CAPITAL ONE BANK
Jan 17, 2020 340518112 Alteration Type II PERMIT ISSUED - ENTIRE JOB/WORK REPLACEMENT OF GAS FIRED BOILER AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILER. THERE WILL BE NO CHANGE IN USE E... $15,460 CAPITAL ONE BANK
Dec 2, 2019 340673373 Alteration Type II SIGNED OFF APPLICATION FILED TO MODIFY EXISTING ATM AREA AND ADD ADDITIONAL ATM MACHINE ALL AS PER PLANS FILED HEREWITH. NO CHAN... $33,000 CAPITAL ONE
Nov 14, 2019 340679643 Alteration Type II SIGNED OFF THIS APPLICATION IS FILED FOR ONLY MECHANICAL HVAC UNIT SUPPLYING THE ATM VESTIBULE ONLY. NO CHANGE TO USE EGRESS OR ... $15,750 CAPITAL ONE
Sep 7, 2017 321055433 Alteration Type II SIGNED OFF INTERIOR RENOVATION TO INCLUDE CONSTRUCTION OF NEW PARTITIONS AND FINISHES AS SHOWN ON PLANS. NO CHANGE IN USE, EGRES... $5,000 CAPITAL ONE
Apr 19, 2017 340494968 Alteration Type II PLAN EXAM - IN PROCESS REPLACEMENT OF GAS FIRED BOILER AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILER. THERE WILL BE NO CHANGE IN USE E... $15,460 CAPITAL ONE BANK
Apr 19, 2017 340495039 Alteration Type II PLAN EXAM - IN PROCESS REPLACEMENT OF GAS FIRED BOILERS AND GAS PIPING RE-CONNECTION TO THE REPLACED BOILERS. THERE WILL BE NO CHANGE IN USE... $27,200 CAPITAL ONE BANK
Apr 11, 2017 340476078 Alteration Type II SIGNED OFF REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY $150,500 CAPITAL ONE BANK
Feb 24, 2017 340476069 Alteration Type II PLAN EXAM - IN PROCESS REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY $150,500 CAPITAL ONE BANK
Dec 27, 2016 340458472 Alteration Type II PLAN EXAM - IN PROCESS REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY $150,500 CAPITAL ONE BANK
Apr 27, 2016 340376578 Alteration Type II PLAN EXAM - IN PROCESS REPLACEMENT OF A/C EQUIPMENT AND COOLING TOWER .THERE WILL BE NO CHANGE IN USE EGRESS OR OCCUPANCY $150,500 CAPITAL ONE BANK