ECB violations
191 Malta Street, Brooklyn • Block 04343 • Lot 0048
32 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Nov 5, 2021 | 35632830M | RESOLVE | CLASS - 2 | FAILURE TO MAINTAIN REOCCURING CONDITION ONSITE ATOI OF EXISTING 2STYBNONACTIVE CONST SITE,I OBSERVED SWS POORLY MAIN... | $0 | $0 | Mar 16, 2022 |
| Apr 16, 2021 | 35551858J | RESOLVE | CLASS - 2 | TEMP CONST EQUIPMENT ONSITE-EXPIRED PERMIT.NOTE-ATOI I OBSERVED SWS INPLACE,UPON REV OF DEPT RECORDS PERMIT HAS BEEN ... | $5,000 | $5,000 | Aug 25, 2021 |
| Apr 16, 2021 | 35551857H | RESOLVE | CLASS - 2 | PEDESTRIAN PROTECTION DOESNT MEET CODE SPECS.NOTE-ATOI RESPONDING TO COMPLAINT OF POORLY MAINTAINED SWS.FOLLOWING HAZ... | $5,000 | $5,000 | Aug 25, 2021 |
| Jan 7, 2021 | 35526108X | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 01/23/18 & TO FILE A CERT OF CORREC... | $3,125 | $3,125 | May 19, 2021 |
| Sep 22, 2020 | 35520779J | RESOLVE | CLASS - 2 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35308789P ISSUED ON 01-23-18 AND TO FI... | $3,125 | $3,125 | Feb 3, 2021 |
| Aug 7, 2020 | 35500563M | RESOLVE | CLASS - 2 | TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXP PERMIT. AT TIME OF INSPECTION OF A 2 STY BLDG I OBSERVED SIDEWALK SHED A... | $5,000 | $5,000 | Dec 16, 2020 |
| Aug 7, 2020 | 35500562K | RESOLVE | CLASS - 2 | SIDEWALK SHED/PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS.AT TIME OF INSPECTION OF A 2 STY BLDG I OBSERVE... | $5,000 | $5,000 | Dec 16, 2020 |
| Dec 28, 2019 | 35456384L | RESOLVE | CLASS - 2 | PEDESTROAM PROTECTION DOES NOT MEET CODE SPECIFICATIONS.AT THE TIME OF INSPECTION OF A 2 STORY BUILDING OBSERVED SIDE... | $5,000 | $5,000 | Dec 3, 2020 |
| Dec 28, 2019 | 35456383J | RESOLVE | CLASS - 2 | TEMPORARY CONSTRUCTION EQUIPMENT ON SITE -EXPIRED PERMIT.AT THE TIME OF INSPECTION OF A 2 STORY BUILDING OBSERVED SID... | $3,125 | $3,125 | Dec 3, 2020 |
| Dec 27, 2019 | 35514560Y | RESOLVE | CLASS - 2 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35308789P ISSUED ON 01-23-2018 AND TO ... | $3,125 | $3,125 | Dec 4, 2020 |
| Nov 13, 2019 | 35459559H | RESOLVE | CLASS - 2 | TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXP PERMIT. OBSERVED SIDEWALKSHED W/NO ACTIVE PERMITS ON SITE OR POSTED OR I... | $3,125 | $3,125 | Sep 11, 2020 |
| Nov 13, 2019 | 35511906Z | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 01-23-18 & TO FILE A C OF C PURSUAN... | $5,000 | $5,000 | Sep 11, 2020 |
| Aug 8, 2019 | 35427040P | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 01-23-18 & TO FILE A C OF C PURSUAN... | $3,125 | $3,125 | Dec 9, 2019 |
| May 30, 2019 | 35399122N | RESOLVE | CLASS - 2 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35308789P ISSUED ON 01/23/18 AND TO FI... | $3,125 | $3,125 | Sep 16, 2019 |
| Jan 7, 2019 | 35390605R | RESOLVE | CLASS - 2 | FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION #35308789P ISSUED 01/23/18 AND TO FILE... | $5,000 | $5,000 | Apr 15, 2019 |
| Sep 4, 2018 | 35388375H | RESOLVE | CLASS - 1 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35309347M ISSUED ON 03/10/18 AND TO FI... | $2,500 | $2,500 | Jun 18, 2019 |
| Sep 4, 2018 | 35388377L | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 01-23-18 & TO FILE A C OF C PURSUAN... | $1,250 | $1,250 | Jun 17, 2019 |
| Sep 4, 2018 | 35388376J | RESOLVE | CLASS - 1 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #32309347M ISSUED ON 03/10/18 AND TO FI... | $0 | $0 | Jun 18, 2019 |
| Jul 18, 2018 | 35341307H | RESOLVE | CLASS - 1 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35309347M ISSUED ON 03/10/18 & TO FILE A C OF C PURSUAN... | $2,500 | $2,500 | Sep 25, 2019 |
| Jul 18, 2018 | 35341309L | RESOLVE | CLASS - 1 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308790M ISSUED ON 01/23/18 & TO FILE A C OF C PURSUAN... | $2,500 | $2,500 | Sep 25, 2019 |
| Jul 18, 2018 | 35341308J | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/ THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIO# 35308789P ISSUED ON 1/23/18 & TO FILE A C OF ... | $1,250 | $1,250 | Sep 25, 2019 |
| Jun 9, 2018 | 35339582J | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 01-22-18 & TO FILE A C OF C PURSUAN... | $1,250 | $1,250 | Sep 25, 2019 |
| Jun 9, 2018 | 35339583L | RESOLVE | CLASS - 1 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35309347M ISSUED ON 03/10/18 & TO FILE A C OF C PURSUAN... | $2,500 | $2,500 | Sep 25, 2019 |
| Jun 9, 2018 | 35339584N | RESOLVE | CLASS - 1 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308790M ISSUED ON 01/23/18 & TO FILE A C OF C PURSUAN... | $2,500 | $2,500 | Sep 25, 2019 |
| May 1, 2018 | 35329122J | RESOLVE | CLASS - 1 | UNLAWFUL ACTS. FAILURE TO COMPLY W/ AN ORDER OF THE COMMISSIONER. FAILURE TO CORRECT CONDITIONS CITED UNDER SUMMONS# ... | $2,500 | $2,500 | Sep 23, 2019 |
| Apr 26, 2018 | 35337989M | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 01-23-18 & TO FILE A C OF C PURSUAN... | $3,125 | $3,125 | Jul 16, 2018 |
| Apr 26, 2018 | 35337711H | RESOLVE | CLASS - 1 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION#35309347M ISSUED ON 09/10/18 AND TO FIL... | $6,250 | $6,250 | Jun 25, 2018 |
| Mar 10, 2018 | 35309346K | RESOLVE | CLASS - 1 | FAILURE TO MAINTAIN BLDG WALLS OR APPURTENANCES AT EXP1 FRONT WALL VERTICAL CRACK FROM GROUND - ROOF LINE (PARAPET WA... | $6,250 | $6,250 | May 7, 2018 |
| Mar 10, 2018 | 35309347M | RESOLVE | CLASS - 1 | WORK W/O PERMIT. WORK NOTED AT FRONT OF PREMISES EXP 1 DOOR LINTEL ANDALL 5 WINDOWS ON 1ST AND 2ND FLOOR LINTEL REMOV... | $4,000 | $4,000 | May 7, 2018 |
| Mar 4, 2018 | 35317386P | RESOLVE | CLASS - 2 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35308789P ISSUED ON 1-23-18 & TO FILE A C OF C PURSUANT... | $2,000 | $2,000 | Sep 19, 2018 |
| Jan 23, 2018 | 35308790M | RESOLVE | CLASS - 1 | WORK W/O PERMIT.WORK NOTED:IN CELLAR LEVEL ERECTED FULL HEIGHT PARTITIONS TO SUBDIVIDE THE OPEN CELLAR AREA TO CREATE... | $4,000 | $4,000 | Sep 19, 2018 |
| Jan 23, 2018 | 35308789P | RESOLVE | CLASS - 1 | 2 FAMI RESIDENCE CONVERTED TO OR MAINTAINED AS A DWELLING FOR 4 OR MORE FAMILIES.DOB RECORDS INDICATES PREMISES IS A ... | $0 | $0 | Dec 9, 2024 |