494-506 East 98 Street, Brooklyn • Block 04718 • Lot 0042
10 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Mar 29, 1999 | 32017378L | ACTIVE | Non-Hazardous | 36,49,19B. BQ9(27-147) CODE SECTION WORK WITHOUT A PERMIT. | $350 | $0 | Oct 4, 1999 |
| Feb 15, 1995 | 34122338Y | ACTIVE | Non-Hazardous | NEW BUILDING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY.REMEDY:OBTAIN A VALID C/O. | $500 | $0 | May 15, 1995 |
| Jun 1, 1992 | 34072160N | RESOLVE | Non-Hazardous | NEW BUILDING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY. REMEDYOBTAIN A VALID CERTIFICATE OF OCCUPANCY. | $0 | $0 | Aug 10, 1992 |
| May 22, 1989 | 34026827P | RESOLVE | Non-Hazardous | NEW BUIDLING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY UNDER NB 825/87. REMEDY: OBTAIN A VALID CERFTIFICATES ... | $500 | $0 | Jul 3, 1989 |
| May 22, 1989 | 34026753L | RESOLVE | Non-Hazardous | NEW BUIDLING OCCUPIED WITHOUT A VALID C OF O. REMEDY: DISCONTINUE USE UNTIL A NEW C OF O IS OBTAINED. | $500 | $0 | Jul 3, 1989 |
| Nov 16, 1988 | 34015132P | RESOLVE | Unknown | FAILURE TO PROVIDE 8' SOLID FOR INTERUPTED CONSTRUCTED OPERATION REMEDY: PROVIDE 8' HIGH FENCE FORTHWITH. | $500 | $0 | Jan 23, 1989 |
| Sep 7, 1988 | 34012303R | RESOLVE | Hazardous | FAILURE TO DO ADEQUATE HOUSEKEEPING SIDEWALK AT EAS SIDE OF LOT APPOX 75 FT COVERED WITH DEBRIS AT DIRT DUE TO CONSTR... | $0 | $0 | Oct 24, 1988 |
| Sep 7, 1988 | 34012302P | RESOLVE | Non-Hazardous | WORK WITHOUT A PERMIT CONSTRUCTION OF 12 BLOCK WALL AT SOUTH AND WEST OF LOT WITHOUT FIRST OBTAINING A PERMIT FROM TH... | $0 | $0 | Oct 24, 1988 |
| Aug 22, 1988 | 34011953Y | RESOLVE | Hazardous | FAILURE TO PROVIDE 8 HIGH FENCE WHERE REQUIRED DURING EXCAVCATION OPERATIONS NOTED EXCAVATED FOR FOOTINGS AND NO ADEQ... | $0 | $0 | Oct 17, 1988 |
| Jul 19, 1988 | 34010476X | RESOLVE | Hazardous | FAILURE TO REMOVE GAT TANKS BELOW GROUND AND IN PROGRESS OF EXCAVATION CAUSING HAZARDOUS WORKING CONDITION REMEDY YOU... | $250 | $0 | Nov 21, 1988 |