ECB violations
537 Brooklyn Avenue, Brooklyn • Block 04793 • Lot 0002
21 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Jul 10, 2025 | 39542209K | RESOLVE | CLASS - 1 | AT THE TIME OF MY INSPECTION OF A 7 STORY NEW BUILDING,I OBSERVED 10 WORKERS AT JOBSITE UPON REQUEST FOR SITE SAFETY ... | $2,515 | $2,515 | Sep 29, 2026 |
| Jul 10, 2025 | 39542210H | ACTIVE | CLASS - 1 | AT THE TIME OF MY INSPECTION OF A 7 STORY NEW BUILDING, I OBSERVED ROOF WORK INCOMPLETE AND AT EXPOSURE #2 THERE WERE... | $5,030 | $5,030 | Sep 29, 2026 |
| May 21, 2025 | 39540503M | RESOLVE | CLASS - 2 | AT THE TIME OF MY INSPECTION I OBSERVED THAT THERE WAS NO OVERHEAD PROTECTION AT EXPOSURE 3 AND THERE WERE WORKERS DO... | $2,530 | $2,530 | Sep 11, 2026 |
| May 21, 2025 | 39540498R | RESOLVE | CLASS - 2 | AT THE TIME OF MY INSPECTION I OBSERVED THAT THERE WAS NO ROOF PROTECTION FOR THE NEIGHBORING PROPERTY AT EXPOSURE 2. | $2,530 | $2,530 | Sep 11, 2026 |
| May 21, 2025 | 39540504Y | RESOLVE | CLASS - 2 | AT THE TIME OF MY INSPECTION I OBSERVED THAT THERE WAS A CHAIN FALL AND A MAKE SHIFT PLAT FORM AND NO DESIGN DRAWINGS... | $2,530 | $2,530 | Sep 11, 2026 |
| May 21, 2025 | 39540505X | RESOLVE | CLASS - 2 | MICELLANEOUS VIOLATIONS. AT THE TIME OF MY INSPECTION I OBSERVED THAT THE GUARDRAI SYSTEM AT THE ELEVATOR SHAFT DID N... | $5,000 | $5,000 | Oct 15, 2026 |
| Aug 15, 2024 | 39531438K | RESOLVE | CLASS - 2 | OBSERVATION: SSP INADEQUATE MISSING DETAILS DRAWINGS AND 1ST FOOR PLAN.MAINTAIN/DISPLAY REQUIRED SITE DOCUMENTS | $1,250 | $1,250 | Jun 1, 2026 |
| Apr 26, 2024 | 39528125M | RESOLVE | CLASS - 2 | CONTRACTOR FAILED TO PROVIDE PROOF OF NEIGHBOR ACCESS AGREEMENT LETTER WHEN REQUESTED, FOR INSTALLATION OF ROOF PROTE... | $1,562 | $1,562 | Jul 10, 2024 |
| Apr 26, 2024 | 39528126Y | RESOLVE | CLASS - 2 | THE ACCUMULATION & STORAGE OF COMBUSTIBLE MATERIALS IN CLOSE PROXIMITY TO MULTIPLE GASOLINE CANISTERS PRESENTING POSS... | $3,125 | $3,125 | Jul 10, 2024 |
| Jan 26, 2024 | 39525177K | RESOLVE | CLASS - 2 | NEW MIX USE 7 STORY BUILDING WITH COMMUNITY FACILITY .OBSERVED: ACTIVE SITE AND PERMIT CP PRESENT .UPON INSPECTION WA... | $6,250 | $6,250 | Apr 3, 2024 |
| Jan 26, 2024 | 39525155J | RESOLVE | CLASS - 2 | NEW 7 STORY MIX USE BUILDING . NOTED AT TIME OF INSPECTION ACTIVE SITE AND PERMIT CP PRESENT UPON INSPECTION WAS REQU... | $10,000 | $10,000 | Oct 7, 2026 |
| Jan 26, 2024 | 39525176Z | RESOLVE | CLASS - 2 | NEW 7 STORY MIX USE BUILDING WITH COMMUNITY FACILITY . OBSERVED: AT TIME OF INSPECTION ACTIVE SITE AND PERMIT CP PRES... | $5,000 | $5,000 | Apr 3, 2024 |
| Dec 27, 2023 | 39524336Y | RESOLVE | CLASS - 2 | AT THE TIME OF MY INSPECTION OF A 7 STORY NEW BUILDING, I OBSERVED SIDEWALK SHED IN PLACE AT EXPOSURE #1 WITH A VALID... | $10,000 | $10,000 | Sep 18, 2026 |
| Oct 6, 2023 | 35674491M | RESOLVE | CLASS - 2 | FAILURE TO PROVIDE PERMANENT STAIN AS NOTED AT TIME OF MY INSPECTION OBSERVED WORK ON 6 FLOOR FRAMING WALLS AND COLUM... | $0 | $0 | Dec 13, 2023 |
| May 17, 2023 | 39516700L | RESOLVE | CLASS - 1 | AT TIME OF INSPECTION AT AN ACTIVE CONSTRUCTION JOB SITE, I OBSERVED GUARDRAILS ON 2ND FLOOR AT EXPOSURE #1 AND #3 WI... | $5,000 | $5,000 | Dec 12, 2024 |
| Mar 22, 2023 | 39514487M | RESOLVE | CLASS - 2 | UPON FURTHER REVIEW OF THE FENCE PLANS, SITE OBSERVATIONS DID NOT CONFORM WITH CONSTRUCTION DOCUMENTS, MISSING AT THE... | $0 | $0 | Jun 7, 2023 |
| Apr 21, 2022 | 35361918P | RESOLVE | CLASS - 2 | NYCBC28-116.2.3 FAILURE TO PROVIDE ADEQUATE INSP PROGRAM TR1.AS NOTED:ATOI@CONST SITE&REVIEWING SUBMITTED SPC INSP RE... | $3,125 | -$3,125 | Oct 12, 2022 |
| Mar 22, 2022 | 35651152X | RESOLVE | CLASS - 2 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS.AS NOTED AT TIME OF INSPECTION AT AN ACTIVE CONSTRUCTION SIT... | $3,125 | $3,125 | Jan 9, 2023 |
| Mar 22, 2022 | 35647274M | RESOLVE | CLASS - 2 | FAILURE TO PERFORM PROPER CONCRETE WASH-OUT WATER PROCEDURES.AS NOTED AT TIME OF INSPECTION AT AN ACTIVE CONSTRUCTION... | $5,000 | $5,000 | Jan 9, 2023 |
| Mar 22, 2022 | 35651151Y | RESOLVE | CLASS - 1 | CONSTRUCTION SUPERINTENDENT FAILED TO PERFORM DUTIES AS PER CODE.AS NOTED AT TIME OF INSPECTION AT AN ACTIVE CONSTRUC... | $12,500 | $12,500 | Jan 3, 2023 |
| Mar 22, 2022 | 35651150M | RESOLVE | CLASS - 1 | FAILURE TO PROVIDE APPROVED CONSTRUCTION DOCUMENTS.AS NOTED AT TIME OFINSPECTION AT AN ACTIVE CONSTRUCTION SITE,OBSER... | $6,250 | $6,250 | Jan 9, 2023 |