ECB violations
862 East 34 Street, Brooklyn • Block 05008 • Lot 0065
24 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Dec 11, 2025 | 39170083J | RESOLVE | CLASS - 2 | ON EXPOSURE #3 FROM 1ST FLOOR TO 4TH FLOOR EXTERIOR WALLS OUTBOARD INSULATION WERE INSTALLED THICKNESS 2" R-VALUE 10 ... | $0 | $0 | Feb 18, 2026 |
| Dec 10, 2025 | 39547829Y | RESOLVE | CLASS - 2 | OBSERVED ACTIVE JOBSITE WITH POWERLINE PROTECTED 3 FEET ON EXPOSURE 2 FEW INCHES AWAY FROM SUPPORTED SCAFFOLD . CONTR... | $2,500 | $2,500 | Dec 14, 2026 |
| Dec 10, 2025 | 39547827K | RESOLVE | CLASS - 2 | NEW 4 STORY BUILDING .OBSERVED ACTIVE SITE CP PRESENT UPON INSPECTION NOTED SWS ERECTED ON EXPOSURE 1 CONTRARY TO APP... | $0 | $0 | Feb 18, 2026 |
| Nov 19, 2025 | 39547130K | RESOLVE | CLASS - 2 | PROPOSED 4 STORY 6 FAMILY DWELING .OBSERVED: ACTIVE SITE CP PRESENT UPON INSPECTION NOTED: SWS EXP 4 COMPLETE DIFFERE... | $0 | $0 | Jan 28, 2026 |
| Oct 14, 2025 | 39545945M | RESOLVE | CLASS - 2 | UPON INSPECTION, OBSERVED SIDEWALK SHED INSTALLED AT EXPOSURE 4 CONTRARY TO BC 3307.6.4.4 (5) SIDEWALK SHED HAS NO HI... | $2,400 | $2,400 | Aug 3, 2026 |
| Oct 14, 2025 | 39545947X | RESOLVE | CLASS - 2 | ACTIVE CONSTRUCTION OPERATIONS OF A 4 STORY, 50FT NEW BUILDING OBSERVED EXPOSURE 2 COMPLETELY EXPOSED WITH NO ADEQUAT... | $2,500 | $2,500 | Aug 3, 2026 |
| Sep 9, 2025 | 39159777R | RESOLVE | CLASS - 2 | UPON INSPECTION ON 09/09/2025, ACCESS TO THE ACTIVE FOUR-STORY NEW BUILDING WORKSITE UNDER PERMIT #321589740 WAS DENI... | $5,000 | $5,000 | May 3, 2027 |
| Sep 9, 2025 | 39159771X | RESOLVE | CLASS - 2 | AT INSPECTION ON 09/09/2025, I (INSPECTOR)OBSERVED WORKERS TRANSPORTING MATERIALS INTO & WORKING 864 E 34TH STREET BK... | $5,000 | $5,000 | May 4, 2027 |
| Jul 16, 2025 | 39542467N | RESOLVE | CLASS - 2 | OBSERVED COLD FORM STEEL OPERATION CURRENTLY AT 3RD FLOOR, BALCONY EXTENDED APPROXIMATELY 8FT OUTWARD FROM FACE OF BU... | $5,000 | $5,000 | Aug 19, 2026 |
| Jul 16, 2025 | 39542469R | RESOLVE | CLASS - 1 | OBSERVED COLD FORM STEEL OPERATION CURRENTLY AT 3RD FL, BALCONY EXTENDED APPROXIMATELY 8FT OUTWARD FROM FACE OF BUILD... | $0 | $0 | Sep 24, 2025 |
| Jul 16, 2025 | 39542459N | RESOLVE | CLASS - 1 | OBSERVED COLD FORM STEEL OPERATION CURRENTLY AT 3RD FL, BALCONY EXTENDED APPROXIMATELY 8FT OUTWARD FROM FACE OF BUILD... | $0 | $0 | Jul 27, 2026 |
| Jul 16, 2025 | 39542468P | RESOLVE | CLASS - 2 | OBSERVED COLD FORM STEEL OPERATION CURRENTLY AT 3RD FLOOR, BALCONY EXTENDED APPROXIMATELY 8 FEET OUTWARD FROM FACE OF... | $1,250 | $0 | Jul 27, 2026 |
| Jul 16, 2025 | 39542458L | RESOLVE | CLASS - 2 | OBSERVED COLD FORM STEEL OPERATION CURRENTLY AT 3RD FLOOR, BALCONY EXTENDED APPROXIMATELY 8 FEET OUTWARD FROM FACE OF... | $625 | $0 | Jul 27, 2026 |
| Jul 16, 2025 | 39542460K | RESOLVE | CLASS - 2 | OBSERVED COLD FORM STEEL OPERATION CURRENTLY AT 3RD FLOOR, BALCONY EXTENDED APPROXIMATELY 8FT OUTWARD FROM FACE OF BU... | $5,000 | $5,000 | Aug 19, 2026 |
| Jun 7, 2025 | 39541185K | RESOLVE | CLASS - 2 | NOTE: AT TIME OF INSPECTION OF A PROPOSED 4 STORY BUILDING AT 1 FLOOR LEVEL, ACTIVE CONSTRUCTION OPERATIONS, UPON REQ... | $5,000 | $5,000 | Sep 16, 2026 |
| Jun 7, 2025 | 39541180L | RESOLVE | CLASS - 1 | I OBSERVED INADEQUATE GUARDRAIL SYSTEM MADE OF CAUTION TAPE ON A LANDING BETWEEN THE GROUND FLOOR AND BASEMENT LEVEL ... | $5,000 | $5,000 | Sep 16, 2026 |
| Jun 7, 2025 | 39541181N | RESOLVE | CLASS - 1 | AT TIME OF INSPECTION, I OBSERVED FOUNDATION WORK HAS BEEN COMPLETED, UPON REVIEWING DEPARTMENT RECORDS NO NOTIFICATI... | $2,500 | $2,500 | Sep 16, 2026 |
| Jun 7, 2025 | 39541231M | RESOLVE | CLASS - 1 | AT TIME OF INSPECTION, I OBSERVED FOUNDATION WORK HAS BEEN COMPLETED (BASEMENT LEVEL), UPON REVIEWING DEPARTMENT RECO... | $2,500 | $2,500 | Sep 16, 2026 |
| Jun 7, 2025 | 39541232Y | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION, I OBSERVED A TEMPORARY PLATFORM IN PLACE WITH INADEQUATE GUARDRAIL SYSTEM MADE OF CAUTION TAPE... | $2,500 | $2,500 | Sep 16, 2026 |
| Jun 7, 2025 | 39541233X | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION, I OBSERVED A TEMPORARY PLATFORM IN PLACE WITH CMU UNITS STORED THROUGHOUT, UPON REQUEST FOR DE... | $2,500 | $2,500 | Sep 16, 2026 |
| Jun 7, 2025 | 39541239R | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION, I OBSERVED A TEMPORARY PLATFORM IN PLACE MADE OUT OFF PLYWOOD NOT MEETING CODE (3315.2) REQUIR... | $2,500 | $2,500 | Sep 16, 2026 |
| Apr 15, 2025 | 39539129N | RESOLVE | CLASS - 2 | UPON INSPECTION OF AN ACTIVE 4 STORY NB IN EXCAVATION PHASE. I OBSERVED ON GOING EXCAVATION WORK AT ALL EXPOSURES. I ... | $1,250 | $0 | Jun 25, 2025 |
| Nov 15, 2024 | 39534433P | RESOLVE | CLASS - 1 | AT THE TIME OF A DEMO SIGN OFF APPOINTMENT, I CHECKED THE SYSTEM AND WASN'T ABLE TO FIND A CALL IN DATE IN DOB OW SYS... | $2,500 | $0 | Jul 21, 2025 |
| May 31, 2019 | 35243469L | ACTIVE | CLASS - 1 | OCCUPANCY CONTRARY THAT ALLOWED C OF O AND DEPT OF BUILDING RECORDS. PARTITION ERECTED CREATING ROOMS FOR LIVING @CEL... | $12,500 | $12,500 | Nov 18, 2019 |