23 Ocean Parkway, Brooklyn • Block 05322 • Lot 0004

69 records

Environmental Control Board violations, which carry a hearing and a penalty.

Issued Violation Status Severity Description Penalty Balance due Hearing
Oct 16, 2025 39546032M RESOLVE CLASS - 2 ATOI, OBSERVED SIDEWALK SHED IN PLACE WITH ACTIVE PERMITS; HOWEVER, INADEQUATE ILLUMINATION WAS NOTED AT EXP#1&2, AS ... $2,400 $2,400 Mar 25, 2027
Oct 8, 2025 39545729H RESOLVE CLASS - 2 ACTIVE JOBSITE, UPON INSPECTION 3314.01. OBSERVED 90FT HIGH SUPPORTED SCAFFOLD AT EXPOSURE 1 NOT ERECTED AND OR MAINT... $2,500 $2,500 Aug 25, 2026
Oct 7, 2025 35685715X RESOLVE CLASS - 1 FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTIONOPERATION. AT EXPOSURE 3 4'X8' SECTION OF WOOD ... $25,000 $25,000 Aug 12, 2026
Jul 5, 2025 39541983P RESOLVE CLASS - 2 9 STORIES NEW BUILDING, WITH A BUILDING FOOTPRINT (SQ. FT.) 15870, WALK JOBSITE PERIMETERS, KNOCK & CALLED OUT, I OBS... $2,500 $0 Apr 27, 2026
Jun 26, 2025 39541716K RESOLVE CLASS - 2 AT TIME OF INSPECTION, OBSERVED UNSAFE CONDITIONS AT EXPOSURE 3, INCLUDING RIPPED NETTING ON SIDEWALK SHED, DEBRIS CA... $2,400 $2,400 Dec 10, 2026
Jun 3, 2025 35693917Y RESOLVE CLASS - 1 FAILURE TO INSTITUTE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY CONSTRUCTION-NO GUARDRAILS. AS NOTED AT TIME OF ... $0 $0 Apr 21, 2026
Apr 12, 2025 39539026K RESOLVE CLASS - 2 BC 3303.3 ATOI OF A 9 STORY NEW BUILDING AT ROOF, BUILDING APPROXIMATELY 15400 SQUARE FEET. SITE CLOSED AND THERE WER... $2,500 $2,500 Jan 15, 2026
Apr 12, 2025 39539027M RESOLVE CLASS - 2 AT THE TIME OF MY INSPECTION OF A 9 STORY NEW BUILDING OBSERVED JERSEY BARRIERS AT EXP#1 AND EXP# 3 NOT MAINTAIN AS P... $1,250 $0 Jan 15, 2026
Apr 1, 2025 39538574R RESOLVE CLASS - 2 AT 4:55AM OBSERVED 9 STORY BUILDING WITH SWS IN PLACE NOTE AT EXP# 3 NOT ALL BULBS THAT WAS ILLUMINATED AT EXP# 4 PED... $625 $625 Jun 16, 2026
Feb 27, 2025 39537353Z RESOLVE CLASS - 2 AT TIME OF INSPECTION OBSERVED PEDESTRIAN PROTECTION SIDEWALK SHED IN PLACE AT PEDESTRIAN OVERPASS BRIDGE. UPON INSPE... $2,400 $0 Jun 16, 2025
Jan 31, 2025 39536504M RESOLVE CLASS - 2 BC 3307.2.6 AT THE TIME OF MY INSPECTION OF A 9 STORY NEW BUILDING, I OBSERVED SIDEWALK SHED IN PLACE AT EXPOSURE #1 ... $5,000 $5,000 Oct 27, 2026
Jan 31, 2025 39536503K RESOLVE CLASS - 2 BC 3309.1 AT THE TIME OF MY INSPECTION OF A 9 STORY NEW BUILDING, I OBSERVED SUPPORTED PIPE SCAFFOLD AT EXPOSURE #1 A... $5,000 $5,000 Oct 27, 2026
Jan 31, 2025 39536505Y RESOLVE CLASS - 1 BC 3303.3 AT THE TIME OF MY INSPECTION OF A 9 STORY NEW BUILDING APPROXIMATELY 15, 400SQ FT. SITE CLOSED NO CONSTRUCT... $5,000 $5,000 Oct 27, 2026
Nov 18, 2024 39534483N RESOLVE CLASS - 1 OBSERVED 9 STORY BUILDING WITH FRONT SETBACK APPROX. 36FT . MISSING SWS AT EXP#1 AND SWS NOT EXTENDED AS PER CODE AT ... $10,000 $10,000 May 19, 2026
Nov 18, 2024 39534482L RESOLVE CLASS - 2 OBSERVED CONSTRUCTION FENCE AT EXP # 2 MISSING NOT FULLY ENCLOSING CONSTRUCTION SITE. CREATES UNAUTHORIZED ACCESS TO ... $1,000 $0 May 19, 2026
Nov 6, 2024 39534186R RESOLVE CLASS - 1 AT THE TIME OF MY INSPECTION OF A 9 STORY NEW BUILDING, I OBSERVED SUPPORTED PIPE SCAFFOLD IN PLACE AT EXPOSURE #1 AN... $625 $0 Feb 26, 2025
Sep 5, 2024 39532105R RESOLVE CLASS - 1 CONTRACTOR FAILED TO PROVIDE ANY DOCUMENTATION OF STANDPIPE BEING PRESSURIZED, NOR DID THEY PROVIDE ANY DOCUMENTATION... $5,000 $0 Jun 26, 2025
Mar 9, 2024 39526294Y RESOLVE CLASS - 2 AT THE TIME OF MY INSPECTION OF A 9 STORY BUILDING AT ROOF LEVEL (APPROXIMATELY 15400 SQUARE FEET) SITE CLOSED AND TH... $2,500 $0 Jul 3, 2024
Jul 21, 2023 39519599J RESOLVE CLASS - 2 AT THE TINE OF MY INSPECTION OF A 9 STORY BUILDING, I OBSERVED AT EXPOSURE #4 SIDEWALK SHED IN WITH A VALID PERMIT DA... $2,400 $0 Nov 1, 2023
Jun 21, 2023 39518021Z RESOLVE CLASS - 2 AT THE TIME OF MY INSPECTION OF A 9 STORY NEW BUILDING, I OBSERVED AT EXPOSURE #3 SIDEWALK SHED IN PLACE WITH A VALID... $2,400 $0 Mar 4, 2024
Feb 6, 2023 39512713M RESOLVE CLASS - 1 AT TIME OF INSPECTION OF A 9 STORY NEW BUILDING FORMING THE ROOF, OBSERVED A WORK AND STORAGE ZONE AT EXPOSURE 3 WITH... $1,250 $0 Mar 5, 2024
Feb 6, 2023 39512710R RESOLVE CLASS - 1 AT TIME OF INSPECTION OF A 9 STORY NEW BUILDING. OBSERVED LARGE AMOUNTS OF CONSTRUCTION DEBRIS ON THE FLOORS IN PLAST... $2,500 $0 Mar 5, 2024
Feb 6, 2023 39512707X RESOLVE CLASS - 1 AT INSPECTION OF A 9 STORY NEW BUILDING FORMING THE ROOF, BUILDING I 90 FEET IN HEIGHT. THE FIRE STANDPIPE STOPPED AT... $0 -$5,000 Mar 5, 2024
Feb 6, 2023 39512706Y RESOLVE CLASS - 1 AT TIME OF INSPECTION OBSERVED A 9 STORY NEW BUILDING, AT EXPOSURE 1 TITAN DEBRIS BOXES ON 6TH AND 7TH LEVELS. UPON R... $0 -$2,500 Mar 5, 2024
Feb 6, 2023 39512705M RESOLVE CLASS - 1 AT INSPECTION FOUND NO EVIDENCE OF FLYING DEBRIS NAILS OR ROCKS NO ACTION NECESSARY. SUMMONS ISSUED OTHER THAN COMPLA... $0 -$2,500 Mar 5, 2024
Jan 5, 2023 39511276Z RESOLVE CLASS - 2 CCD1 WAS APPROVED ON 11/04/2022. INADEQUATE DETAIL IN SITE SAFETY PLAN PAGE SSP-004 DETAIL 18 AS PER OPTION ONE ON CC... $625 $0 Aug 21, 2023
Dec 21, 2022 35593352H RESOLVE CLASS - 1 FAILURE TO SAFEGUARD.AT TIME OF INSPECTION,OBSERVED CONCRETE PIECE FELL ON ADJACENT BUILDING 151 CLIFTON PLACE ROOF.P... $10,030 $0 Mar 4, 2024
Dec 21, 2022 35593351X RESOLVE CLASS - 1 UNLAWFULLY CONTINUE WORK WHILE ON NOTICE OF STOP WORK ORDER.AT TIME OFINSPECTION OBSERVED AT 6 FLOOR AT EXP4 CLOSE TO... $5,000 $0 Feb 15, 2024
Dec 9, 2022 39510218X RESOLVE CLASS - 1 INSPECTION OF AN 9 STORY BUILDING AT 6 FLOOR LEVEL WITH WORK IN PROGRESS , I OBSERVED AT EXPOSURE 4 AND SIDEWALK SHED... $2,400 $0 Nov 15, 2023
Dec 9, 2022 39510220P RESOLVE CLASS - 1 INSPECTION OF AN 9 STORY AT 6 FLOOR LEVEL WITH WORK IN PROGRESS, OBSERVED AT FLOOR LEVEL STAIR ARE INSTALLED, UPON RE... $0 -$2,500 Feb 13, 2024
Dec 9, 2022 39510219H RESOLVE CLASS - 2 INSPECTION OF AN 9 STORY BUILDING WITH ACTION WORK IN PROGRESS, OBSERVED REVIEW SITE SAFETY PLAN DON'T REFLECT THE LO... $0 $0 Feb 15, 2023
Oct 19, 2022 39507886Y RESOLVE CLASS - 2 AT THE TIME OF MY I OBSERVED SIDEWALK SHED/ OVERHEAD PROTECTION IN PLACE AT EXPOSURE # 4 WITH A VALID PERMIT : DATE 0... $2,400 $0 Feb 22, 2023
Oct 19, 2022 39507885M RESOLVE CLASS - 1 28-105.12.8 MISC VIOLATION.AT THE TIME OF MY INSPECTION OF A 21 STORY NEW BUILDING AT EXCAVATION PHASE,I OBSERVED CHA... $1,000 $0 May 10, 2023
Sep 6, 2022 39506015Y RESOLVE CLASS - 1 AT TIME OF MY INSPECTION I OBSERVED A PROPOSED 9 STORY NEW BUILDING CURRENTLY WORKING ON 3RD FLOOR DECK AND FRAMING U... $0 $0 Oct 16, 2023
Sep 6, 2022 39506012Z RESOLVE CLASS - 1 ATOI I OBSERVED A PROPOSED 9 STORY NB WITH AN ACTIVE JOB SITE. CURRENTLY WORKING ON 3RD FLOOR DECK AND FRAMING FOR 4T... $625 $0 May 1, 2023
Aug 31, 2022 39505854K RESOLVE CLASS - 1 I OBSERVED ACTIVE CONSTRUCTION SITE AND AT EXP. #3 SIDEWALK SHED IN PLACE NOT EXTENDED 5 FEET OVER ADJOINING PROPERTY... $2,500 $0 Jan 4, 2023
Jul 12, 2022 39503418P RESOLVE CLASS - 1 I OBSERVED ACTIVE CONSTRUCTION SITE AT FOUNDATION PHASE, UPON REVIEW OF SITE SAFETY PLAN IT WAS NOT REFLECTION SIT CO... $2,500 $0 Nov 15, 2022
Jun 30, 2022 39065088Y RESOLVE CLASS - 1 THE SITE CAUSED DAMAGE TO THE ADJACENT PREMISE 51 CATON PLACE, CRACKED INTERIOR SLAB ALONG THE EXPOSURE 4 WALL AT TIM... $12,500 $0 Nov 2, 2022
Apr 13, 2022 35648044L RESOLVE CLASS - 1 FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQUIRED BY CHAPTER 33.AT TIME OF INSPECTION OF PROPOSED NEW BUILDING U... $2,530 $0 Sep 7, 2022
Apr 13, 2022 35648045N RESOLVE CLASS - 2 BC3307.2.1 FAILURE TO COMPLY WITH DOT REGULATIONS S PER 34 RCNY 2-05 & ADMIN CODE PROVISIONS 19-107,19-108 OR 19-121.... $0 $0 Sep 7, 2022
Apr 13, 2022 35648043J RESOLVE CLASS - 1 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APROVED AMENDMENTS.AT TIME OF INSPECTION PROPOSED NEW... $2,530 $0 Sep 7, 2022
Jan 5, 2022 35636887L RESOLVE CLASS - 2 TEMP CONST EQUIPMENT ONSITE-EXPIRED PERMIT.ATOI ONSITE,I OBSERVED CONST FENCE IN PLACE AROUND PERIMETER OF SITE.UPON ... $0 $0 May 18, 2022
Mar 18, 2021 35551219N RESOLVE CLASS - 2 TEMP CONST EQUIPMENT ONSITE EXPIRED PERMIT.NOTE-@TIME OF INSP I OBSERVED CONST FENCE IN PLACE.UPON REV OF DEPT RECORD... $3,125 $0 Jul 28, 2021
Oct 20, 2020 35522022R RESOLVE CLASS - 2 NEILURE TO COMPLY WITH COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#35454680R ISSUED ON 9/12/19 AND TO FILE A ... $625 $0 Mar 3, 2021
Apr 27, 2020 35491753L RESOLVE CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. AT THEOF MY INSPECTION OF A 3 STY DEMO SITE I OBSERVE... $5,000 $0 Sep 2, 2020
Mar 26, 2020 35480962Y RESOLVE CLASS - 1 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS &/OR APPROVEDAMENDMENTS. AT THE TIME OF INSPECTION OF A 3 ST... $2,500 $0 Jan 11, 2021
Mar 26, 2020 35480963X RESOLVE CLASS - 1 SEC. 3306.9.12 REMOVAL OF MATERIALS. AT THE TIME OF INSPECTION OF A 3 STY DM JOBSITE. OBSERVED LARGE AMOUNT OF DEBRIS... $2,500 $0 Jan 11, 2021
Mar 26, 2020 35480964H RESOLVE CLASS - 1 SEC. 3306.9.8.3 GLASS. AT THE TIME OF INSPECTION OF A 3 STY DM JOBSITEOBSERVED WORKERS PERFORMING DEMOLITION OPERATIO... $2,500 $0 Jan 11, 2021
Jan 7, 2020 35515500R RESOLVE CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35407936J ISSUED ON 04-03-2019 AND TO FILE... $1,250 $0 Dec 17, 2020
Oct 31, 2019 35511659K RESOLVE CLASS - 2 FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35407936J ISSUED ON 04-03-19 & TO FILE A C OF C PURSUAN... $1,250 $0 Mar 4, 2020