ECB violations
1160 47 Street, Brooklyn • Block 05627 • Lot 0053
14 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Jan 9, 2026 | 39549015Y | ACTIVE | CLASS - 2 | OBSERVED THAT NO CONSTRUCTION FENCE WAS INSTALLED ALONG EXP 1 OF THE SITE, AS REQUIRED TO SAFEGUARD THE PUBLIC AND SE... | $1,000 | $1,000 | Oct 13, 2026 |
| Jan 9, 2026 | 39549025H | ACTIVE | CLASS - 2 | AT TIME OF INSPECTION NO OVERHEAD PROTECTION WAS PROVIDED FOR THE ADJOINING PROPERTY @ THE CORNER OF EXP 2 & 3. OBSER... | $5,000 | $5,000 | Oct 13, 2026 |
| Jan 9, 2026 | 39549039Z | ACTIVE | CLASS - 2 | OBSERVED THAT THE CONSTRUCTION SHANTY ON THE BASEMENT OF THE SITE WAS NOT CONSTRUCTED OF FIRE RATED MATERIALS AS REQU... | $1,250 | $1,250 | Oct 13, 2026 |
| Jan 9, 2026 | 39549013K | ACTIVE | CLASS - 2 | AT TIME OF INSPECTION REQUESTED CONSTRUCTION SUPER LOGS WERE NOT MAINTAIN ON SITE AS REQUIRED. ALSO CS FAILED TO APPO... | $5,000 | $5,000 | Oct 13, 2026 |
| Jan 9, 2026 | 39549038R | ACTIVE | CLASS - 2 | AT TIME OF INSPECTION, IT WAS OBSERVED THAT THE CONSTRUCTION SITE FAILED TO HAVE REQUIRED DESIGN DRAWINGS FOR THE INS... | $1,250 | $1,250 | Oct 13, 2026 |
| Jan 9, 2026 | 39549020Z | ACTIVE | CLASS - 1 | IT WAS OBSERVED THAT THE CONSTRUCTION SITE FAILED TO HAVE A REQUIRED SITE SAFETY PLAN AND NO DAILY LOGS ON SITE AVAIL... | $2,500 | $2,500 | Oct 13, 2026 |
| Jan 9, 2026 | 39549022M | ACTIVE | CLASS - 1 | AT THE TIME OF INSPECTION, IT WAS OBSERVED THAT THE CONSTRUCTION SITE FAILED TO PROVIDE A REQUIRED SIDEWALK SHED ALON... | $4,800 | $4,800 | Oct 13, 2026 |
| Nov 25, 2025 | 39547333K | ACTIVE | CLASS - 1 | 3314.4.4.12 EXPOSED ELECTRICAL WIRE AT EXPOSER #1.STOP ALL WORK AT EXPOSER #1 SIDE WALK SHED | $10,000 | $10,000 | Feb 5, 2027 |
| Nov 25, 2025 | 39547330P | ACTIVE | CLASS - 1 | BC 3314.1 AT THE TIME OF MY INSPECTION OF A 3-STORY BUILDING, I OBSERVED PIPE SCAFFOLD AT EXP# 1 NOT MAINTAINED, WITH... | $10,000 | $10,000 | Feb 4, 2027 |
| Nov 25, 2025 | 39547331R | ACTIVE | CLASS - 2 | BC3307.2.1 AT THE TIME OF MY INSPECTION OF A 3-STORY BUILDING, I OBSERVED MATERIAL STORED ON THE SIDEWALK, BLOCKING A... | $10,000 | $10,000 | Feb 4, 2027 |
| Nov 25, 2025 | 39547334M | ACTIVE | CLASS - 1 | WORK CONTRARY TO PIPE SCAFFOLD PLANS. STOP ALL WORK ON SUPPORTED PIPE SCAFFOLDING AT EXPOSER #1 | $12,500 | $12,500 | Feb 5, 2027 |
| Jun 26, 2025 | 39541713P | ACTIVE | CLASS - 2 | AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING UNDER ALTERATION , I OBSERVED THERE WERE NO OVERHEAD PROTECTION PR... | $5,000 | $5,000 | Oct 16, 2026 |
| Jun 26, 2025 | 39541712N | ACTIVE | CLASS - 2 | BC 3309.11 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING UNDER ALTERATION , I OBSERVED THERE WERE NO TREE PROTEC... | $10,000 | $10,000 | Mar 4, 2027 |
| Aug 12, 2023 | 39520493J | RESOLVE | CLASS - 2 | AT TIME OF INSPECTION, I OBSERVED CONTAINER ON STREETS AT EXPOSURE #1 FILLED AND NOT COVERED./ COVER CONTAINER. | $3,125 | $3,125 | Sep 23, 2024 |