ECB violations
Bay Ridge Prep Upper School, Brooklyn • Block 05936 • Lot 0016
4 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Aug 7, 2026 | 39557659J | ACTIVE | CLASS - 2 | AT THE TIME OF INSPECTION, OBSERVED SIDEWALK SHED IN PLACE INSTALLED AT EXP# 3&4, BUT NOT IN CONFORMANCE WITH THE DEP... | $1,250 | $1,250 | Oct 14, 2026 |
| Aug 7, 2026 | 39557658H | ACTIVE | CLASS - 1 | AT THE TIME OF INSPECTION, OBSERVED A TEMPORARY PEDESTRIAN WALKWAY AT EXP# 1 ALONG SHORE RD. BUT WAS NOT ADEQUATELY M... | $1,250 | $1,250 | Oct 14, 2026 |
| Dec 22, 2025 | 35717848N | RESOLVE | CLASS - 1 | FAILURE TO INSTITUTE SAFETY EQUIP MEASURES OR TEMPORARY CONSTRUCTION NO GUARDRAILS. AS NOTED: AT TIME OF INSPECTION A... | $5,000 | $0 | Feb 25, 2026 |
| Dec 22, 2025 | 35726375R | RESOLVE | CLASS - 1 | BC 1905.6.3.2. FAILURE TO REMOVE STRENGHT TESTING CYLINDERS STORE FOR A PERIOD UP TO 120 HOURS ON SITE. AS NOTED: AT ... | $2,500 | $0 | Feb 25, 2026 |