ECB violations
38-02-38-20 43 Avenue, Queens • Block 00219 • Lot 0025
17 records
Environmental Control Board violations, which carry a hearing and a penalty.
| Issued | Violation | Status | Severity | Description | Penalty | Balance due | Hearing |
|---|---|---|---|---|---|---|---|
| Jun 11, 2025 | 39541297P | RESOLVE | CLASS - 2 | BC 3307.4.7 BARRIERS: INSPECTION OF AN ACTIVE SITE WITH EQUIPMENT, TRUCKS, CONTAINERS AND MATERIAL IN THE ROADWAY, I ... | $2,500 | $0 | Mar 12, 2026 |
| Jun 11, 2025 | 39541294J | RESOLVE | CLASS - 1 | BC3307.1 PEDESTRIAN PROTECTION: DURING INSPECTION OF AN ACTIVE SITE WITH A SIDEWALK SHED IN PLACE, MATERIAL, EQUIPMEN... | $5,000 | $0 | Mar 12, 2026 |
| Jun 11, 2025 | 39541296N | RESOLVE | CLASS - 2 | BC 3303.4.2 CONTAINERS: DURING INSPECTION I OBSERVED TWO DEBRIS CONTAINERS ON THE STREET NOT FULLY ENCLOSED BY BARRIE... | $2,500 | $0 | Mar 12, 2026 |
| Jun 11, 2025 | 39541295L | RESOLVE | CLASS - 2 | BC3303.3WATCHPERSON: DURING INSPECTION OF AN ACTIVE SITE APPROXIMATELY 52029 SQUARE FEET I REQUESTED TO SEE THE WATCH... | $2,500 | $0 | Mar 12, 2026 |
| Apr 21, 2025 | 39539461P | RESOLVE | CLASS - 2 | OBSERVED WORKERS INSTALLING CMU BLOCK AT LEADING EDGE WITH SAFETY HARNESSES CONNECTED TO A MAKE-SHIFT ROPE TIED TO A ... | $5,030 | $5,030 | Jan 28, 2027 |
| Apr 21, 2025 | 39539466Y | RESOLVE | CLASS - 2 | OBSERVED LARGE AMOUNT OF STRUCTURAL STEEL I-BEAMS BEING STORED/ PLACED ON EXCAVATED RAMP & SOIL IN CLOSE PROXIMITY TO... | $2,530 | $2,530 | Nov 16, 2026 |
| Apr 21, 2025 | 39539468H | RESOLVE | CLASS - 2 | 3301.5. OBSERVED AERIAL OPERATIONS PERFORMED BY MOBILE CRANE, RIGGING STRUCTURAL STEEL ABOVE WORKERS W/OUT CAZ, NO HO... | $2,530 | $2,530 | Nov 16, 2026 |
| Apr 21, 2025 | 39539467X | RESOLVE | CLASS - 2 | OBSERVED UNDERPINNING @ EXPO 3, EXISTING WALL W/ LARGE OPENING W/OUT SHORING SURROUNDED BY STRUCTURAL STEEL I-BEAMS &... | $1,280 | $1,280 | Jan 28, 2027 |
| Apr 21, 2025 | 39539420Z | RESOLVE | CLASS - 2 | OBSERVED ACTIVE CRANE OPERATIONS WITHOUT LICENSED LIFT-DIRECTOR, LICENSED MASTER-RIGGER OR MASTER RIGGER FOREMAN AS P... | $1,280 | $1,280 | Nov 16, 2026 |
| Mar 4, 2025 | 39537573K | RESOLVE | CLASS - 2 | OBSERVED UNSAFE ACTIVE CONSTRUCTION OPERATIONS @ EXPOSURE 2 CLOSE PROXIMITY LARGE OPENINGS THAT CROSS BETWEEN STALLED... | $5,000 | $5,000 | Dec 1, 2026 |
| Mar 4, 2025 | 39537578J | RESOLVE | CLASS - 2 | DURING INSPECTION IT WAS OBSERVED CS DANIEL KAYKOV FAILED TO PERFORM DUTIES AS PER CODE FAILURE TO SAFEGUARD PUBLIC A... | $5,000 | $5,000 | May 13, 2025 |
| Jan 6, 2025 | 39134630L | RESOLVE | CLASS - 2 | AT TIME OF AUDIT FOR CD-5668, CN-1204/23, PERSON ACTING AS LIFT DIRECTOR WAS NOT LICENSED AS LIFT DIRECTOR, MASTER RI... | $1,250 | $0 | Oct 21, 2025 |
| Jan 6, 2025 | 39134645Y | RESOLVE | CLASS - 2 | AT TIME OF AUDIT FOR CD-5668, CN-1204/23, PERSON ACTING AS LIFT DIRECTOR WAS NOT LICENSED AS LIFT DIRECTOR, MASTER RI... | $1,250 | $630 | Mar 18, 2025 |
| Nov 14, 2024 | 39130276J | RESOLVE | CLASS - 2 | ATOI OBSERVED OUTBOARD INSULATION WERE INSTALLED WITH ADJACENT PROPERTY @ EXP#2 REQUESTED APPROVED EN NOT PROVIDED., ... | $1,250 | $0 | Jan 21, 2025 |
| Nov 4, 2024 | 39534159L | RESOLVE | CLASS - 2 | CRANE OPERATIONS IN PROGRESS STRUCT.STEEL BUILDING ABOVE FENCE LINE WITH SWS MISSING PARAPET WALL REQ.PERBC3307.6.4.6... | $2,400 | $0 | Oct 9, 2025 |
| Oct 1, 2024 | 37029872R | RESOLVE | CLASS - 1 | FAILURE TO SUBMIT THE REQUIRED PARKING STRUCTURE INITIAL OBSERVATION REPORT FOR AN EXISTING PARKING STRUCTURE DOCUMEN... | $0 | $0 | Jun 12, 2025 |
| Jun 18, 2024 | 39529730P | RESOLVE | CLASS - 1 | ON-SITE FOR DEMO SIGN-OFF APPOINTMENT FOR A ONE-STORY BUILDING. BUILDING IS FULLY DEMOLISHED WITH FULL BACKFILL OF CL... | $2,500 | $0 | Aug 27, 2024 |