| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Nov 26, 2021 | 421559076 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | THIS PERMIT APPLICATION REPRESENTS THE WORK INVOLVED WITH THE INSTALLATION OF FIRE SERVICE PIPING AS IT IS RUN FROM T... | $646,736 | CON EDISON COMPANY OF NEW YORK |
| Jun 19, 2019 | 421608727 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | LEGALIZATION OF EXISTING AUTOMATIC SMOKE DETECTION FIRE ALARM SYSTEM FOR JAMAI CA SUBSTATION IN COMPLIENCE WITH FDNY ... | $10,000 | CON EDISON |
| May 16, 2019 | 421546624 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | CONSTRUCT A FIRE PUMP EQUIPMENT ENCLOSURE TO BE LOCATED AT THE SOUTH - EAST PORTION OF THE LOT AT CON EDISON'S JAMAIC... | $217,338 | CONSOLIDATED EDISON COMPANY OF N |
| May 16, 2019 | 421581096 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | PERFORM CIVIL WORK NECESSARY TO UPGRADE SPCC MEASURES AT CON EDISON'S JAMAICA SUBSTATION. CONSTRUCTION INCLUDES FORMI... | $468,797 | CON EDISON COMPANY OF NEW YORK |
| May 16, 2019 | 421568663 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | PERFORM SPRINKLER AND CIVIL WORK TO INSTALL A NEW DELUGE SYSTEM AT CON EDISON'S JAMAICA SUBSTATION. SPRINKLER WORK IN... | $196,976 | CON EDISON COMPANY OF NEW YORK |
| Aug 10, 2017 | 440424177 | Alteration Type II | PLAN EXAM - DISAPPROVED | CONSTRUCT A NEW STAND ALONE FIRE PROTECTION EQUIPMENT ENCLOSURE WITH A 3 HOUR FIRE RATING. THE ENCLOSURE WILL CONSIST... | $217,338 | CON EDISON COMPANY OF NEW YORK |
| Aug 1, 2017 | 440423944 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | CONSTRUCT / INSTALL A NEW STAND - ALONE FIRE PUMP ENCLOSURE WITH A 3 HOUR FIRE RATING. THE ENCLOSURE WILL CONSIST OF ... | $217,338 | CON EDISON COMPANY OF NEW YORK |
| May 31, 2017 | 440409256 | Alteration Type II | APPLICATION PROCESSED - ENTIRE | CONSTRUCT A FIRE PROTECTION EQUIPMENT ENCLOSURE. | $250,000 | CON EDISON COMPANY OF NEW YORK |
| Jun 24, 2015 | 440210291 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | REPLACE PORTION OF PERIMETER WALL AND FENCING; INSTALLATION OF FOUNDATIONS FOR SECURITY CAMERAS AT CON EDISON'S JAMAI... | $157,177 | CON EDISON CO OF NEW YORK, INC. |
| Apr 7, 2009 | 402502886 | Alteration Type II | SIGNED OFF | Structural steel replacement for breakers. There is no change in use, egress, occupancy or floor area under this appl... | $37,100 | Con Edison |
| Aug 5, 2008 | 410137365 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | RELOCATE EXISTING CURB CUT AT THE CON EDISON,JAMAICA SUBSTATION.THE NEW CURB C UT IS 28 FEET WIDE WITH 2 FOOT SPLAYS ... | $0 | CONSOLIDATED EDISON COMPANY |
| Jun 11, 2008 | 410094455 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | GENERAL CONSTRUCTION AT THE JAMAICA SUBSTATION OF EQUIPMENT FOUNDATIONS, RISER , STRUCTURES AND INSTALLATION OF CHAIN... | $220,000 | CONSOLIDATED EDISON COMPANY |
| Sep 17, 2007 | 402517273 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | Installation of new fuel storage tank for the emergency generator set. There is no change in use, egress, occupancy o... | $16,000 | Consolidated Edison Co. of NY |
| Nov 16, 2004 | 402035953 | Alteration Type II | PLAN EXAM - DISAPPROVED | INSTALLTION OF NEW FUEL STORAGE TANK FOR THE EMERGENCY GENERATOR SET. T ERE IS NO CHAGNE IN USE, EGRESS, OCCUPAN CY O... | $16,000 | CON EDISON COMPANY OF NY |