Skip to content

ECB violations

135-54 Centreville Street, Queens • Block 11518 • Lot 0026

33 records

Environmental Control Board violations, which carry a hearing and a penalty.

Issued Violation Status Severity Description Penalty Balance due Hearing
Jul 8, 2026 39556313H ACTIVE CLASS - 2 GENERAL CONTRACTOR FAILED TO FILE A CERTIFICATE OF CORRECTION WITH THE DOB FOR VIOLATION# 39551363N ISSUED 03/06/2026... $1,250 $1,250 Sep 15, 2026
May 14, 2026 39554132J ACTIVE CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS.... $1,280 $1,280 Jul 21, 2026
Mar 6, 2026 39551361J ACTIVE CLASS - 1 WORK WITHOUT A PERMIT. OBSERVED: ACTIVE SITE CP PRESENT AT TIME OF INSPECTION NOTED FOUNDATION WALLS DONE EXCEPT CORN... $12,500 $12,500 Jun 2, 2026
Mar 6, 2026 39551367K ACTIVE CLASS - 2 OBSERVED: ACTIVE SITE CP PRESENT UPON INSPECTION NOTED INADEQUATELY FIRE EXTINGUISHERS NOT PER NYC FIRE CODE UNITS NO... $2,530 $2,530 Mar 16, 2027
Mar 6, 2026 39551368M ACTIVE CLASS - 1 OBSERVED ACTIVE SITE , UPON INSPECTION NOTED A GREAT AMOUNT ON MATERIAL DEBRIS IN DIFERENTS LOCATION , WOOD AND 2X4 A... $2,530 $2,530 Mar 16, 2027
Mar 6, 2026 39551369Y ACTIVE CLASS - 2 OBSERVED: NO PEDESTRIAN PROTECTION DURING CONCRETE OPERATIONS NO FLAG PERSON NO SIGNANGE , STOP ALL CONCRETE OPERATIO... $5,030 $5,030 Mar 16, 2027
Mar 6, 2026 39551376M ACTIVE CLASS - 2 OBSERVED:CONSTRUCTION SUPERINTENDENT WAZIR KHAN REGISTRATION 27464 FAILED TO PERFORM DUTIES .FOUND SITE WITH MULTIPLE... $5,030 $5,030 Mar 23, 2027
Mar 6, 2026 39551363N ACTIVE CLASS - 1 OBSERVED: SOE WORK HAS BEEN DONE 85% APPROXIMATELY EXCEPT ON CORNER EXP1,2 , UPON REVIEW DRAWINGS NOTED MISSING WALLE... $2,530 $2,530 Mar 16, 2027
Mar 6, 2026 39551364P ACTIVE CLASS - 2 OBSERVED: ACTIVE SITE WITHOUT SSP, SOE AND FOUNDATIONS DRAWINGS ,NO OPTICAL MONITORING & VIBRATION INSPECTION REPORTS... $1,280 $1,280 Mar 16, 2027
Jan 29, 2026 39549624J RESOLVE CLASS - 2 NEW COMMUNITY FACILITY BUILDING .OBSERVED SITE CLOSED NO ONGOING CONSTRUCTION ACTIVITY , UPON EXTERIOR INPECTION NOTE... $2,500 $2,500 Mar 16, 2027
Jan 29, 2026 39549623H RESOLVE CLASS - 2 NEW COMMUNITY FACILITY BUILDING .OBSERVED SITE CLOSED NO ONGOING CONSTRUCTION ACTIVITY , UPON EXTERIOR INPECTION NOTE... $5,000 $5,000 Mar 16, 2027
Dec 26, 2025 39548502R ACTIVE CLASS - 1 BC3301.13.5 ALTERNATE SUPER: DURING INSPECTION OF AN ACTIVE SITE I REQUESTED TO SEE THE SUPERINTENDENT AND THE COMPET... $5,000 $5,000 Oct 16, 2026
Jun 10, 2025 39541281K RESOLVE CLASS - 2 I OBSERVED A FENCE INSTALLED AT EXPOSURE 1 NOT CONSTRUCTED OR MAINTAINED ACCORDING TO CODE. INCORRECT SIZED VIEWING P... $1,000 $1,000 Aug 19, 2025
Jun 3, 2025 39540965R RESOLVE CLASS - 2 GC FAIL TO FILE CERTIFICATE OF CORRECTION WITH THE DOB. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION# 39538911Z ISS... $1,250 $1,250 Mar 10, 2026
Jun 3, 2025 39540968M RESOLVE CLASS - 2 GC FAIL TO FILE CERTIFICATE OF CORRECTION WITH THE DOB. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION# 39538912K ISS... $1,250 $1,250 Mar 10, 2026
Jun 3, 2025 39540963N ACTIVE CLASS - 2 GC FAIL TO FILE CERTIFICATE OF CORRECTION WITH THE DOB. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION# 39538910R ISS... $1,250 $1,250 Mar 10, 2026
Jun 3, 2025 39540966Z RESOLVE CLASS - 2 GC FAIL TO FILE CERTIFICATE OF CORRECTION WITH THE DOB. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION# 39538914Y ISS... $1,250 $1,250 Mar 10, 2026
Apr 9, 2025 39538912K RESOLVE CLASS - 1 DURING INSPECTION OF A SITE UNDER SOE PHASE, I OBSERVED THAT THERE WERE NO GUARDRAILS BC 3304.4.4BC 3315.2.2 AROUND T... $5,000 $5,000 Mar 10, 2026
Apr 9, 2025 39538911Z RESOLVE CLASS - 1 BC 3303.7.2 FIRE EXTINGUISHERS: DURING INSPECTION OF AN ACTIVE SITE AT SOE PHASE, WITH A LOT OF WOOD, DEBRIS AND 2 CO... $5,000 $5,000 Mar 10, 2026
Apr 9, 2025 39538916H RESOLVE CLASS - 2 BC 3313.1 FLAMMABLE AND COMPRESSED GASES: DURING INSPECTION OF AN ACTIVE SITE AT SOE PHASE, I OBSERVED 2 COMBUSTIBLE ... $2,500 $2,500 Aug 12, 2025
Apr 9, 2025 39538914Y RESOLVE CLASS - 1 BC 3301.2 SAFETY MEASURES: DURING INSPECTION OF AN ACTIVE SITE AT SOE PHASE, I OBSERVED 4 WORKERS STANDING ON TOP WHA... $5,000 $5,000 Aug 12, 2025
Apr 9, 2025 39538909J RESOLVE CLASS - 2 BC 3315.1 RAMPS AND RUNWAYS: DURING INSPECTION OF AN ACTIVE SITE AT SOE PHASE, I OBSERVED THAT THERE WAS NO WALKING R... $2,500 $2,500 Aug 12, 2025
Apr 9, 2025 39538921M RESOLVE CLASS - 1 DURING INSPECTION OF AN ACTIVE SOE SITE ON A STOP WORK ORDER, IT WAS DISCOVERED THAT THE ELECTRICAL POLE AT EX#2 WAS ... $10,000 $10,000 Oct 13, 2026
Apr 9, 2025 39538910R ACTIVE CLASS - 1 DURING INSPECTION OF AN ACTIVE SITE AT SOE PHASE, I OBSERVED 5 WORKERS ONSITE, 4 STANDING ON TOP A WALL BRACED WITH W... $10,000 $10,000 Mar 10, 2026
Sep 27, 2024 39125962N RESOLVE CLASS - 2 CONSTRUCTION ACTIVITIES NEAR THE POWER/ELECTRICAL POLE ARE IN VIOLATION OF NYC ELECTRICAL CODE 2020, CHAPTER 27, AND ... $625 $625 Jan 7, 2025
Sep 26, 2024 39532827Z RESOLVE CLASS - 2 INSPECTION OF A SITE @ EXCAVATION PHASE, I NOTICED THAT THE GATE HAD A HANGING CHAIN AND WAS UNLOCKED; WHEN I ENTERED... $5,000 $5,000 Jan 7, 2025
Sep 26, 2024 39532830J RESOLVE CLASS - 2 DURING INSPECTION OF A SITE AT EXCAVATION PHASE, I OBSERVED THAT THERE WAS A LARGE ADVERTISEMENT POSTER AFFIXED TO TH... $2,500 $2,500 Jan 7, 2025
Sep 25, 2024 39125835K RESOLVE CLASS - 2 AT TIME OF INSPECTION AT EXP.3 (REAR OF SITE) AND EXP.4 (RIGHT SIDE OF SITE) OBSERVED OPEN, UNPROTECTED EXCAVATED ARE... $2,500 $2,500 Jan 7, 2025
Sep 4, 2024 39532058N RESOLVE CLASS - 2 OBSERVED CONSTRUCTION FENCE INSTALLED AT EXP# 1 2 3 4 UPON REVIEWED TO DOB RECORDS INDICATED TEMPORARY CONSTRUCTION F... $0 $0 Nov 12, 2024
May 13, 2024 39528552R RESOLVE CLASS - 1 AT INSPECTION, IT WAS OBSERVED: EXCAVATION AND PILE-DRIVEN WORK ON-GOING AT JOBSITE AND UPON REQUEST FOR EARTHWORK NO... $2,500 $2,500 Jan 21, 2025
May 13, 2024 39528555M RESOLVE CLASS - 2 AT INSPECTION, IT WAS OBSERVED: CS (WAZIR KHAN) HAS FAILED TO PERFORM HIS DUTIES AS PER BC 3301.13.9, HE FAILED TO CO... $5,000 $5,000 Jul 15, 2025
May 13, 2024 39528554K RESOLVE CLASS - 2 AT INSPECTION, IT WAS OBSERVED: STRUCTURAL H-STEEL PIPE ON EXPOSURES 3 & 4 TOWERING ABOVE THE FENCE RANGING BETWEEN A... $5,000 $5,000 Jul 15, 2025
May 13, 2024 39528553Z RESOLVE CLASS - 2 AT INSPECTION, IT WAS OBSERVED: UPON REQUEST FOR THE APPROVED SOE DRAWINGS NONE WAS AVAILABLE OR PRESENTED AT JOBSITE... $1,250 $1,250 Jul 15, 2025