DOB NOW filings
Epic High School South, Queens • Block 11714 • Lot 0100
25 records
Work filed through DOB NOW, the system that replaced BIS.
| Filed | Filing | Type | Status | Cost | Applicant | Owner |
|---|---|---|---|---|---|---|
| Nov 20, 2025 | Q01169525-P2 | Alteration | Approved | $10,000 | PETER FOSTER | NYC SCHOOL CONSTRUCTION |
| Nov 20, 2025 | Q01169522-P2 | Alteration | Approved | $25,000 | PETER FOSTER | NYC SCHOOL CONSTRUCTION |
| Oct 8, 2025 | Q08021425-P7 | Alteration | Approved | $1,499,820 | Jitendra Agarwal | NYC SCHOOL CONSTRUCTION |
| Aug 25, 2025 | Q08021425-P5 | Alteration | Approved | $1,499,820 | Jitendra Agarwal | NYC SCHOOL CONSTRUCTION |
| Aug 20, 2025 | Q08021425-P6 | Alteration | Approved | $199,920 | gabriel massa | NYC SCHOOL CONSTRUCTION |
| May 16, 2025 | Q01169522-P1 | Alteration | Approved | $25,000 | PETER FOSTER | NYC SCHOOL CONSTRUCTION |
| May 16, 2025 | Q01169525-P1 | Alteration | Approved | $10,000 | PETER FOSTER | NYC SCHOOL CONSTRUCTION |
| Jan 23, 2025 | Q01169525-I1 | Alteration | Permit Entire | $10,000 | PETER FOSTER | NYC SCHOOL CONSTRUCTION |
| Jan 23, 2025 | Q01169522-I1 | Alteration | Permit Entire | $25,000 | PETER FOSTER | NYC SCHOOL CONSTRUCTION |
| Dec 19, 2024 | Q08021425-P1 | Alteration | Approved | $1,499,820 | Jitendra Agarwal | NYC SCHOOL CONSTRUCTION |
| Dec 19, 2024 | Q08021425-P4 | Alteration | Approved | $199,920 | gabriel massa | NYC SCHOOL CONSTRUCTION |
| Dec 19, 2024 | Q08021425-P3 | Alteration | Approved | $74,970 | SUSAN BACAS | NYC SCHOOL CONSTRUCTION |
| Dec 19, 2024 | Q08021425-P2 | Alteration | Approved | $89,985 | Jitendra Agarwal | NYC SCHOOL CONSTRUCTION |
| May 4, 2023 | Q00769023-P2 | Alteration | Approved | $30,000 | Michael McNamara | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Jan 24, 2023 | Q08021425-S3 | Alteration | Permit Entire | $199,920 | gabriel massa | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Jan 23, 2023 | Q08021425-S2 | Alteration | Permit Entire | $74,970 | SUSAN BACAS | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Jan 20, 2023 | Q08021425-I1 | Alteration | Approved | $1,499,820 | Jitendra Agarwal | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Jan 20, 2023 | Q08021425-S1 | Alteration | Permit Entire | $89,985 | Jitendra Agarwal | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Nov 29, 2022 | Q00712716-P1 | Alteration | Approved | $30,000 | Ed Conn | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Nov 4, 2022 | Q00712716-P2 | Alteration | Objections | $499,999 | Ed Conn | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Sep 6, 2022 | Q00769023-P1 | Alteration | Approved | $30,000 | Michael McNamara | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Jul 5, 2022 | Q00769023-I1 | Alteration | Approved | $30,000 | Michael McNamara | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Apr 28, 2022 | Q00712716-S1 | Alteration | Permit Entire | $30,000 | Ed Conn | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Apr 28, 2022 | Q00712716-S2 | Alteration | Permit Entire | $499,999 | Ed Conn | NYC SCHOOL CONSTRUCTION AUTHORITY |
| Apr 19, 2022 | Q00712716-I1 | Alteration | Permit Entire | $1,787,900 | MARIA BAPTISTA | NYC SCHOOL CONSTRUCTION AUTHORITY |