Job filings
120 Precinct Stationhouse, Staten Island • Block 00009 • Lot 0028
18 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Jul 12, 2019 | 540163017 | Alteration Type II | PLAN EXAM - APPROVED | FURNISH & INSTALL ONE (1) AIR COOLED CHILLER, EXHAUST FAN, MAKEUP AIR UNIT, CASSETE AC UNITS, CHILLED WATER PIPIN... | $1,200,000 | NYPD BMS |
| Oct 18, 2018 | 540105633 | Alteration Type III | SIGNED OFF | INSTALLATION OF PIPE SCAFFOLDING AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDE... | $0 | N.B.A CONSTRUCTION INC |
| Oct 18, 2018 | 540105483 | Alteration Type III | SIGNED OFF | PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL CO... | $0 | N.B.A CONSTRUCTION INC |
| Mar 16, 2018 | 540025747 | Alteration Type III | SIGNED OFF | INSTALLATION OF SIDEWALK SHED AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER T... | $0 | DEPT. OF DESIGN & CONSTRUCTION |
| Feb 26, 2018 | 520243102 | Alteration Type II | SIGNED OFF | FILING FOR FACADES AND ROOF RESTORATION TO THE 120TH POLICE PRECINCT STATION. AS SHOWN ON DRAWINGS FILED HEREWITH. NO... | $1,711,764 | NYC DEPT. OF DESIGN & CONSTRUCTI |
| Jun 1, 2016 | 540105474 | Alteration Type III | PLAN EXAM - IN PROCESS | PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL CO... | $0 | N.B.A CONSTRUCTION INC |
| Mar 26, 2015 | 540068111 | Alteration Type II | PLAN EXAM - APPROVED | FURNISH AND INSTALL ONE (1) 60 TON AIR COOLED CHILLER UNIT, TWO(2) AIR HANDLING FAN COIL UNITS, THIRTEEN (13) HYDRONI... | $450,000 | NYPD |
| Feb 11, 2013 | 520120912 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE 2008 CODE. NO CHANGE IN USE, ... | $0 | NYCDDC |
| Oct 2, 2012 | 520112155 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF 46 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR BUILDING ALTERATION, FILED SEPARATELY. LIVE LOAD 300 P... | $0 | YORK SCAFFOLD EQUIPMENT CORP. |
| Aug 24, 2012 | 510068613 | Alteration Type II | SIGNED OFF | — | $450,000 | NYCDDC |
| Apr 11, 2012 | 510071921 | Alteration Type II | SIGNED OFF | PROPOSE TO INSTALL NEW, DRY CHEMICAL OVERHEAD FIRE SUPPRESSION SYSTEM TO PROTECT GASOLINE FUELING AREA OF SERVICE STA... | $10,000 | NYCDDC |
| Sep 17, 2010 | 520048010 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | PROPOSED INSTALLATION OF HEAVYDUTY SIDEWALK SHED FILED FOR REMEDIAL REPAIRS AS PER PLANS. NO CHANGE IN USE OCCUPANCY ... | $0 | NEW YORK POLICE DEPARTMENT |
| Aug 8, 2006 | 500636582 | Alteration Type II | SIGNED OFF | FILED HEREWITH FACADE, ENTRANCE, ND WALK WAYS RENOVATIONS AS PER PLANS. O CHANGE OF USE,EGRESS, OR OCCUPANCY.SCA FFOL... | $2,700,000 | NYC DEPT OF DESIGN & CONST. |
| Apr 26, 2005 | 500694439 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | WE SHALL INSTALL PIPESCAFFOLDING APPX. 54' HIGH. THERE WILL BE NO CHANGE IN USE, EGRESS, OR OCCUPANCY. | $0 | DEPT OF DESIGN AND CONSTRUCTION |
| Jan 3, 2005 | 500694420 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | WE SHALL INSTALL 400 LINEAR FEET OF HEAVYDUTY SIDEWALK SHED. IT WILL BE USED FOR EXTERIOR FACADE REPAIR. THERE WILL B... | $0 | DEPT OF DESIGN AND CONSTRUCTION |
| Mar 15, 2004 | 500576192 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | TO CONVERT PRESENT BOILER FROM OIL TO OI L & GAS FUELS. NO CHANGES TO YS OCCUPANCY OR EGRESS | $25,000 | NEW YORK CITY POICE DEPARTMENT |
| Sep 24, 2003 | 500594163 | Alteration Type II | SIGNED OFF | CLOSE IN PLACE 550 GALLON FUEL OIL UST. INSTALL NEW 550 GALLON FUEL OIL UST.UPGRADE 5,000 GALLON FUEL OIL AST. INSTAL... | $170,000 | NYCDDC |
| May 30, 2003 | 500469414 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | Install 365 linear feet of temporary sidewalk shed to repair building facade . No changes to uses, egress or occupancy. | $15,000 | Dept. Design & Construction |