Job filings
Arthur Kill Road, Staten Island • Block 07247 • Lot 0001
74 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Aug 1, 2025 | 520461875 | Demolition | PERMIT ISSUED - ENTIRE JOB/WORK | — | $0 | INDUSTRIAL DEVELOPMENT ADVANTAGE |
| Aug 1, 2025 | 520461893 | Demolition | PERMIT ISSUED - ENTIRE JOB/WORK | — | $0 | INDUSTRIAL DEVELOPMENT ADVANTAGE |
| Aug 1, 2025 | 520461884 | Demolition | PERMIT ISSUED - ENTIRE JOB/WORK | — | $0 | INDUSTRIAL DEVELOPMENT ADVANTAGE |
| Oct 13, 2020 | 520388697 | Alteration Type II | SIGNED OFF | TO REMOVE PIPING, NO CHANGE IN USE, EGRESS OR OCCUPANCY | $2,760,000 | KINDER MORGAN INC. |
| Jun 30, 2020 | 520390498 | Alteration Type II | SIGNED OFF | REMOVE EXISTING 4,000 GALLON UNDERGROUND STORAGE TANK AND ALL APPURTENANCES. BACKFILL EXCAVATION WITH DGA. RESTORE AS... | $14,000 | KINDER MORGAN STATEN ISLAND TERM |
| Apr 4, 2019 | 540113544 | Alteration Type II | SIGNED OFF | INSTALLATION OF GROUND MOUNT PV ARRAY. INSTALL SOLAR MODULES AND GROUND MOUNT RACKING SYSTEM. INSTALL INVERTERS AND S... | $4,806,000 | KINDER MORGAN LIQUID TERMINALS |
| Apr 3, 2019 | 540114062 | Alteration Type II | SIGNED OFF | CLEARING AND GRADING OF THE SITE IN PREPARATION OF SOLAR PANEL INSTALLATION. O FF SITE FILL REQUIRED. | $500,000 | KINDER MORGAN LIQUID TERMINALS |
| May 1, 2018 | 520289036 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | MODIFICATIONS TO BULK FUEL STORAGE TANK NO. 16, INCLUDING THREE NEW TANK NOZZLES AND A WELDED STEEL LOW SUCTION LINE. | $47,000 | KINDER MORGAN LIQUIDS TERMINALS |
| Apr 30, 2018 | 520196449 | Alteration Type II | SIGNED OFF | INSTALLATION OF POLY UREA CONTAINMENT LINERS FOR BULK STORAGE TANKS NOS. 54 AND 59. | $200,000 | KINDER MORGAN LIQUID TERMINALS |
| Apr 30, 2018 | 520212378 | Alteration Type II | SIGNED OFF | PUMPS 29 & 30 MANIFOLD WELDED STEEL PIPING MODIFICATIONS | $90,000 | KINDER MORGAN LIQUID TERMINALS |
| Apr 10, 2018 | 520256758 | Alteration Type II | SIGNED OFF | 1.REMOVE POST INDICATOR VALVE UPPER ASSEMBLY INCLUD'G POST HEAD & UPPER BARREL 2.INSTALL NEW UPPER BARREL & A... | $13,000 | KM PHOENIX HOLDINGS LLC |
| Mar 26, 2018 | 520256730 | Alteration Type II | SIGNED OFF | DOCK LINE EXTENSION PROJECT AT A PETROLEUM BULK STORAGE FACILITY. FABRICATION AND INSTALLATION OF WELDED STEEL PIPING... | $190,000 | KINDER MORGAN LIQUIDS TERMINALS |
| Mar 26, 2018 | 520240043 | Alteration Type II | SIGNED OFF | BULK STORAGE TANK #1 MODIFICATIONS. FABRICATION AND INSTALLATION OF WELDED STEEL PIPING | $55,000 | KINDER MORGAN LIQUIDS TERMINALS |
| Mar 8, 2017 | 520221046 | Alteration Type III | PERMIT ISSUED - ENTIRE JOB/WORK | WORK INCLUDES THE CLEARING OF TREES, BRUSH AND VEGETATION BETWEEN THE EXISTING CURB AND THE ARTHUR KILL ROAD NORTHERL... | $0 | KINDER MORGAN LIQUID TERMINALS |
| Aug 25, 2016 | 540111261 | Alteration Type II | PLAN EXAM - IN PROCESS | INSTALLATION OF A 2.6 MEGAWATT GROUND MOUNTED SOLAR ARRAY FIELD | $1,250,000 | ENTER SOLAR |
| Jan 28, 2016 | 520240034 | New Building | PLAN EXAM - DISAPPROVED | NEW OFFICE BUILDING AT BULK STORAGE FACILITY INCLUDING FOUNDATION PILES, CONCRETE FOUNDATIONS, STRUCTURAL STEEL, ELEV... | $0 | KINDER MORGAN LIQUIDS TERMINALS |
| Jan 6, 2016 | 520206777 | Alteration Type II | SIGNED OFF | INSTALLATION OF SIX INCH DIAMETER WELDED STEEL TRANSMIX PETROLEUM PIPELINE | $120,000 | KINDER MORGAN LIQUID TERMINALS |
| Dec 11, 2015 | 520165400 | Alteration Type II | SIGNED OFF | INSTALLATION OF HDPE CONTAINMENT LINERS FOR BULK STORAGE TANKS NOS. 43, 56, AN D 60. | $300,000 | KINDER MORGAN LIQUID TERMINALS |
| Dec 11, 2015 | 520244049 | Alteration Type II | SIGNED OFF | REPLACE (IN-KIND) THE EXISTING HVAC UNIT (QTY 1) WITH ONE (1) NEW AIR CONDITIONING UNIT. A VIOLATION WAS ISSUED REQUE... | $18,600 | KINDER MORGAN LIQUID TERMINALS |
| Dec 11, 2015 | 520164820 | Alteration Type II | SIGNED OFF | BULK STORAGE TANK #49 MODIFICATIONS AND REPAIRS. WELDED STEEL LOW SUCTION PIPING FABRICATION AND INSTALLATION | $90,000 | KINDER MORGAN LIQUID TERMINALS |
| Nov 6, 2015 | 520209596 | Alteration Type II | SIGNED OFF | OFFICE REHABILITATION AS A RESULT OF HURRICANE SANDY. WORK INCLUDES PARTIAL REPLACEMENT OF WALLS, DOORS, CEILINGS, FL... | $177,000 | KINDER MORGAN LIQUID TERMINALS |
| Nov 6, 2015 | 520216560 | Alteration Type II | SIGNED OFF | FABRICATION AND INSTALLATION OF TWENTY (20) INCH DIAMETER WELDED STEEL PIPE EXPANSION LOOP IN "A" PIPELINE. | $85,000 | KINDER MORGAN LIQUIDS TERMINALS |
| May 14, 2015 | 520240025 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | POLY UREA CONTAINMENT LINERS FOR CONTAINMENT AREAS FOR TANK NOS. 4, 9 AND 44. | $750,000 | KINDER MORGAN LIQUIDS TERMINALS |
| May 5, 2015 | 520187100 | Alteration Type II | SIGNED OFF | INSTALL A NEW 8,000 GALLON STEEL ABOVEGROUND FIREGUARD TANK, SEVEN STEEL DRIP PANS AT DOCK BERTHS, AND STEEL WELDED P... | $244,000 | KINDER MORGAN LIQUID TERMINALS |
| May 5, 2015 | 520211137 | Alteration Type II | SIGNED OFF | BULK STORAGE TANK NO. 54 INTERNAL FLOATING ROOF | $80,000 | KINDER MORGAN LIQUID TERMINALS |
| Mar 31, 2015 | 520200041 | Alteration Type II | SIGNED OFF | INSTALLATION OF 8FT TALL CHAIN LINK FENCE | $96,000 | KINDER MORGAN LIQUID TERMINALS |
| Jan 21, 2015 | 520187119 | Alteration Type II | SIGNED OFF | BULK STORAGE TANK #61 MODIFICATIONS. WELDED STEEL LOW SUCTION PROCESS PIPING FABRICATION AND INSTALLLATION. | $55,000 | KINDER MORGAN LIQUID TERMINALS |
| Dec 24, 2014 | 520212387 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | POLY UREA CONTAINMENT LINERS FOR CONTAINMENT AREAS FOR TANK NOS. 50, 53, 57 AND 58 | $950,000 | KINDER MORGAN LIQUID TERMINALS |
| Aug 12, 2014 | 520201219 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | FILING FOR THE FULL DEMOLITION OF OIL/WATER TANKS INCLUDING SLAB, DEBRIS REMOVAL & BACKFILL AS PER PLANS FILED HE... | $150,000 | KINDER MORGAN LIQUID TERMINALS |
| Aug 1, 2014 | 520161823 | Alteration Type II | SIGNED OFF | BULK STORAGE TANK #14 MODIFICATIONS AND REPAIRS. WELDED STEEL LOW SUCTION PIPING FABRICATION AND INSTALLATION. | $59,170 | KINDER MORGAN LIQUID TERMINALS |
| Jan 7, 2014 | 520147582 | Alteration Type II | SIGNED OFF | BULK STORAGE TANK #62 MODIFICATIONS AND REPAIRS. WELDED STEEL LOW SUCTION PIPING FABRICATION AND INSTALLATION. | $122,000 | KINDER MORGAN LIQUID TERMINALS |
| Dec 30, 2013 | 520164811 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALLATION OF MANUAL AND AUTOMATIC SMOKE DETECTION FIRE ALARM SYSTEM FOR GAR AGE/OFFICE BUILDING. | $8,000 | KINDER MORGAN LIQUID TERMINALS |
| Nov 19, 2013 | 520127988 | Alteration Type II | SIGNED OFF | OUTDOOR INSTALLATION OF 16 INCH DIAMETER WELDED STEEL PROCESS PIPING, STRAINER AND VALVES. CONSTRUCTION OF CONCRETE F... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| Sep 20, 2013 | 520145209 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING FILED TO REPAIR DAMAGED CAUSED BY HURRICANE SANDY TO THE EXISTING FOAM BUILDING. N... | $80,000 | KINDER MORGAN LIQUID TERMINALS |
| Aug 15, 2013 | 520148233 | Alteration Type II | PLAN EXAM - DISAPPROVED | FIRE ALARM SYSTEM REPAIR. REPLACE THREE (3) PULL STATIONS IN KIND. REPLACE EXISTING NOTIFIER PANEL TO THE CENTRAL STA... | $8,000 | KINDER MORGAN LIQUID TERMINALS |
| Jul 17, 2013 | 520113109 | Alteration Type II | SIGNED OFF | OUTDOOR REPLACEMENT OF AN 8 INCH DIAMETER WELDED STEEL FIRE PROTECTION HEADER AT A PETROLEUM BULK STORAGE FACILITY. T... | $230,000 | KINDER MORGAN LIQUID TERMINALS |
| Nov 9, 2012 | 520108927 | Alteration Type II | SIGNED OFF | TRANSFER JUMP-OVER PIPING FOR BULK PETROLEUM STORAGE TANKS 7, 9 & 10. FABRICATE AND INSTALL 12 INCH DIAMETER CARB... | $55,000 | KINDER MORGAN LIQUID TERMINALS |
| May 2, 2012 | 520097519 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #18. THERE IS NO CHANGE TO... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| May 2, 2012 | 520097500 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #17. THERE IS NO CHANGE TO... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| May 2, 2012 | 520093700 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #45. THERE IS NO CHANGE TO... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| Sep 22, 2011 | 520069979 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | INSTALL NEW TURBINE GENERATOR, WASTE STEAM GENERATOR AND NATURAL GAS METERING STATION. INSTALL NATURAL GAS PIPING TO ... | $458,000 | KINDER MORGAN LIQUID TERMINALS I |
| Jul 7, 2011 | 520014564 | Alteration Type II | SIGNED OFF | — | $1,190,000 | KINDER MORGAN LIQUID TERMINALS |
| Jul 7, 2011 | 520045488 | Alteration Type II | SIGNED OFF | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK#7. THERE IS NO CHANGE TO U... | $65,000 | KINDER MORGAN LIQUID TERMINALS |
| Jul 7, 2011 | 520044069 | Alteration Type II | SIGNED OFF | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY PIPING TO EXISTING PETROLEUM STORAGE TANKS. THERE IS NO CHANGE... | $130,000 | KINDER MORGAN LIQUID TERMINALS |
| Jul 7, 2011 | 520043355 | Alteration Type II | SIGNED OFF | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #13.THERE IS NO CHANGE TO ... | $155,000 | KINDER MORGAN LIQUID TERMINALS |
| May 5, 2011 | 520063939 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #15. THERE IS NO CHANGE TO... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| May 5, 2011 | 520063920 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #51. THERE IS NO CHANGE TO... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| Mar 24, 2011 | 520060852 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #9. THERE IS NO CHANGE TO ... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| Mar 2, 2011 | 520058785 | Alteration Type II | PERMIT ISSUED - ENTIRE JOB/WORK | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY THE EXISTING PETROLEUM STORAGE TANK #44. THERE IS NO CHANGE TO... | $50,000 | KINDER MORGAN LIQUID TERMINALS |
| Oct 4, 2010 | 510066170 | Alteration Type II | SIGNED OFF | HEREWITH THIS APPLICATION IS BEING SUBMITTED TO MODIFY TANK # 55, INSTALLATION OF NEW SUMP PUMP, PIPING AND NOZZLES. ... | $178,000 | KINDER MORGAN LIQUID TERMINALS |