Job filings
770 Broadway • Block 00554 • Lot 0001
380 records
Work filed with the Department of Buildings under its legacy BIS system.
| Latest action | Job | Type | Status | Work | Cost | Owner |
|---|---|---|---|---|---|---|
| Nov 8, 2024 | 120812914 | Alteration Type II | SIGNED OFF | MODIFICATION TO EXISTING DORMA DOOR. NO CHANGE IN USE OR OCCUPANCY | $75,000 | VORNADO REALTY |
| Oct 16, 2024 | 124039977 | Subdivision Condominiums | COMPLETED | TAX LOT SUBDIVISION FOR CONDOMINIUM PURPOSES ONLY. FORMERLY KNOWN AS TAX LOT 1, NOW KNOWN AS TAX LOTS 1001, 1002 AND ... | $0 | 770 BROADWAY OWNER LLC |
| Aug 22, 2024 | 140839261 | Alteration Type II | SIGNED OFF | FILING FOR KITCHEN RANGEHOOD FIRE SUPPRESSION FOR ELECTRIC COOKING EQUIPMENT WITH VENTLESS HOOD, AS SHOWN ON PLAN. NO... | $4,500 | 770 BROADWAY OWNER LLC |
| Aug 15, 2024 | 120614111 | Alteration Type II | SIGNED OFF | VAULT REPAIR AS INDICATED ON ATTACHED DRAWINGS. THE SIDEWALK REPLACEMENT ,FILED WITH DOT, IS NOT PART OF THIS FILING.... | $170,000 | VORNADO OFFICE MANAGEMENT |
| Aug 15, 2024 | 120843123 | Alteration Type II | SIGNED OFF | — | $100,000 | VORNADO OFFICE MANAGEMENT |
| May 15, 2024 | 123092535 | Alteration Type III | SIGNED OFF | INSTALLATION OF PIPE SCAFFOLD FRAMES AS SHOWN ON DRAWING. THERE WILL BE NO CHANGE IN USE, EGRESS OR OCCUPANCY. WE SHA... | $0 | 770 BROADWAY OWNER LL |
| May 8, 2024 | 140599350 | Alteration Type III | SIGNED OFF | INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. ALL WORK SHALL BE ACCORDING TO CHAPTER #33 OF THE 2014 NYC BUILDING CODE.... | $0 | ROCK GROUP NY CORP |
| May 3, 2024 | 140883275 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY STAIRWELL PROTECTION AS PER DRAWINGS. TEMPORARY STAIRWELL PROTECTION SHALL COMPLY WITH CHAP... | $0 | SAFWAY ATLANTIC LLC |
| May 2, 2024 | 140837343 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY SUSPENDED WORK PLATFORM AS PER DRAWINGS. TEMPORARY SUSPENDED WORK PLATFORM SHALL COMPLY WIT... | $0 | SAFWAY ATLANTIC LLC |
| May 2, 2024 | 121231023 | Alteration Type III | SIGNED OFF | INSTALLATION OF A TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUP... | $0 | SAFWAY ATLANTIC LLC |
| May 1, 2024 | 123668290 | Alteration Type II | SIGNED OFF | MECHANICAL MODIFICATIONS AT 10TH FLOOR MECHANICAL EQUIPMENT ROOM AS INDICATED ON DRAWINGS. NO CHANGE TO USE, EGRESS O... | $459,000 | VORNADO OFFICE MANAGEMENT |
| May 1, 2024 | 140883122 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY ROOF ENCLOSURE AS PER DRAWINGS. TEMPORARY ROOF ENCLOSURE SHALL COMPLY WITH CHAPTER #33 OF T... | $0 | SAFWAY ATLANTIC LLC |
| May 1, 2024 | 140883113 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY TROLLEY BEAM SYSTEM AS PER DRAWINGS. TEMPORARY TROLLEY BEAM SYSTEM SHALL COMPLY WITH CHAPTE... | $0 | SAFWAY ATLANTIC LLC |
| Apr 24, 2024 | 140486338 | Alteration Type III | SIGNED OFF | INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND ROOF PROTECTION AS PER PLANS. LIVE LOAD 300 PSF. SIDEWALK SHED AND PROTE... | $0 | ROCK GROUP NY CORP |
| Mar 28, 2024 | 120419608 | Alteration Type II | SIGNED OFF | STRUCTURAL WORK ASSOCIATED WITH THE EXTENSION OF AN EXISTING CONVENIENCE STAIR FROM THE 12TH AND 11TH FLOOR TO THE 10... | $82,500 | VORNADO OFFICE MANAGEMENT |
| Feb 14, 2024 | 123030406 | Alteration Type II | SIGNED OFF | ADDITION/MODIFICATION OF THE EXISTING FIRE ALARM SYSTEM ON THE ROOF AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, E... | $15,000 | VORNADO OFFICE MANAGEMENT |
| Jul 27, 2023 | 141021123 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $0 | VORNADO REALTY TRUST |
| Feb 14, 2023 | 123063763 | Alteration Type II | SIGNED OFF | FIRE ALARM MODIFICATIONS TAKING PLACE ON THE 2ND FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCU... | $3,500 | VORNADO OFFICE MANAGEMENT |
| Jan 26, 2023 | 123589571 | Alteration Type II | SIGNED OFF | ADDITION AND MODIFICATION TO AN EXISTING FIRE ALARM SYSTEM | $150,000 | VORNADO OFFICE MANAGEMENT |
| Jan 24, 2023 | 123458007 | Alteration Type II | SIGNED OFF | FIRE ALARM MODIFICATIONS TAKING PLACE ON THE 10TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCC... | $90,000 | VORNADO OFFICE MANAGEMENT |
| Jan 4, 2023 | 122414627 | Alteration Type II | SIGNED OFF | MODIFICATION TO EXISTING FIRE ALARM SYSTEM AS PER PLANS FILED HEREWITH. NO CHA NGE IN USE, EGRESS OR OCCUPANCY UNDER ... | $150,000 | VORNADO OFFICE MANAGEMENT |
| Jul 11, 2022 | 123540105 | Alteration Type II | SIGNED OFF | INTERIOR ALTERATIONS ON 4TH FLOOR FOR "OATH" AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. | $1,500,000 | VORNADO OFFICE MANAGEMENT |
| Feb 28, 2022 | 123729162 | Alteration Type II | SIGNED OFF | MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UN... | $10,000 | VORNADO REALTY TRUST |
| Feb 23, 2022 | 140911182 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION ALTERATIONS RELATED TO ELEVATOR LOBBY RENOVATIONS ON THE 5TH, 6TH, AND 9TH FLOORS; RELATED WORK ... | $80,000 | VORNADO OFFICE MANAGEMENT |
| Feb 3, 2022 | 123540098 | Alteration Type II | SIGNED OFF | MODIFICATIONS TO SPRINKLER SYSTEM ON 4TH FLOOR (OATH) AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, EGRESS, OR O... | $70,000 | VORNADO OFFICE MANAGEMENT |
| Feb 2, 2022 | 123842887 | Alteration Type II | SIGNED OFF | PROPOSED DEMOLITION OF NON-LOAD-BEARING PARTITIONS AT CELLAR AS INDICATED ON DRAWINGS. NO CHANGE TO USE, EGRESS, OR O... | $115,750 | VORNADO OFFICE MANAGEMENT |
| Jan 19, 2022 | 140849205 | Alteration Type III | SIGNED OFF | INSTALLATION OF TEMPORARY WORK PLATFORM AS PER DRAWINGS. TEMPORARY WORK PLATFORM SHALL COMPLY WITH CHAPTER #33 OF THE... | $0 | SAFWAY ATLANTIC LLC |
| Aug 31, 2021 | 123766228 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION, MECHANICAL AND PLUMBING MODIFICATIONS TAKING PLACE IN THE SUB CELLAR AND 3RD FLOOR AS INDICATED... | $1,180,000 | VORNADO OFFICE MANAGEMENT |
| Jul 1, 2021 | 123732121 | Alteration Type II | SIGNED OFF | MECHANICAL AND PLUMBING ALTERATIONS ON THE 1ST AND 2ND FLOORS AND CELLAR LEVEL RELATED TO RENOVATION OF 9TH STREET BU... | $188,950 | VORNADO OFFICE MANAGEMENT |
| Jun 8, 2021 | 123783147 | Alteration Type II | SIGNED OFF | SPRINKLER MODIFICATIONS TAKING PLACE IN THE SUB CELLAR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCU... | $30,000 | VORNADO OFFICE MANAGEMENT |
| May 27, 2021 | 123188246 | Alteration Type II | SIGNED OFF | DEMOLITION AND CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 14TH & 15TH FLOORS AS INDICATED ON THE DRAWINGS. | $14,300,000 | VORNADO OFFICE MANAGEMENT |
| May 10, 2021 | 123864951 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE ROOF AS INDICATED PER PLANS FILED HERE WITH. NO CHANGE IN USE,... | $1,205,775 | VORNADO OFFICE MANAGEMENT |
| Apr 29, 2021 | 123677075 | Alteration Type II | SIGNED OFF | ADDITIONS/MODIFICATIONS TO FIRE ALARM SYSTEM ON THE 4TH FLOOR (OATH) AS INDICATED ON DRAWINGS. NO CHANGE TO USE, EGRE... | $25,000 | VORNADO OFFICE MANAGEMENT |
| Mar 30, 2021 | 123837893 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 1ST & 2ND FLOORS AS INDICATED PER PLANS FILED HERE WITH. N... | $2,029,000 | VORNADO OFFICE MANAGEMENT |
| Mar 30, 2021 | 123660270 | Alteration Type III | SIGNED OFF | INSTALLATION OF MARQUEE AS INDICATED ON PLANS FILED HEREWITH. NO CHANGE TO EGRESS OCCUPANCY OR USE. | $150,000 | VORNADO OFFICE MANAGEMENT |
| Mar 15, 2021 | 123862597 | Alteration Type II | SIGNED OFF | SPRINKLER MODIFICATIONS TAKING PLACE IN THE SUB CELLAR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCU... | $6,000 | VORNADO OFFICE MANAGEMENT |
| Mar 12, 2021 | 123250926 | Alteration Type II | SIGNED OFF | MODIFICATION TO SPRINKLER SYSTEM AT 10TH FLOOR MECHANICAL EQUIPMENT ROOM AS INDICATED ON DRAWINGS. NO CHANGE TO USE, ... | $12,000 | VORNADO OFFICE MANAGEMENT |
| Mar 2, 2021 | 123190199 | Alteration Type II | SIGNED OFF | STRUCTURAL WORK TO FILL IN SLAB OPENINGS ON PART OF THE 2ND AND 3RD FLOORS IN CONJUNCTION WITH REMOVAL OF ESCALATORS. | $130,000 | VORNADO OFFICE MANAGEMENT |
| Mar 1, 2021 | 140891872 | Alteration Type II | SIGNED OFF | INTERIOR RENOVATION TO EXISTING SPACE AS PER SUBMITTED DRAWINGS. NO CHANGE OF USE, EGRESS OR OCCUPANCY. | $250,000 | VORNADO OFFICE MANAGEMENT |
| Feb 18, 2021 | 123737484 | Alteration Type II | SIGNED OFF | STANDPIPE MODIFICATIONS TAKING PLACE ON THE 1ST & 2ND FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS... | $25,000 | VORNADO OFFICE MANAGEMENT |
| Feb 18, 2021 | 123837884 | Alteration Type II | SIGNED OFF | SPRINKLER MODIFICATIONS TAKING PLACE ON THE 1ST & 2ND FLOOR AS INDICATED ON TH E DRAWINGS. NO CHANGE IN USE, EGRE... | $75,000 | VORNADO OFFICE MANAGEMENT |
| Feb 17, 2021 | 121790598 | Alteration Type I | PERMIT ISSUED - ENTIRE JOB/WORK | FILING HEREWITH TO ESTABLISH PLACE OF ASSEMBLY AND REVISE OCCUPANT LOAD ON THE 8TH FLOOR. INSTALLATION OF INTERIOR PA... | $6,640,000 | VORNADO OFFICE MANAGEMENT |
| Feb 9, 2021 | 123162638 | Alteration Type II | SIGNED OFF | FIRE ALARM MODIFICATIONS TAKING PLACE ON THE 14TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCC... | $280,000 | VORNADO OFFICE MANAGEMENT |
| Feb 8, 2021 | 123766219 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION, MECHANICAL AND PLUMBING MODIFICATIONS TAKING PLACE ON THE 7 & 8TH FLOORS AS INDICATED PER P... | $325,000 | VORNADO OFFICE MANAGEMENT |
| Feb 8, 2021 | 123901947 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION, MODIFICATIONS TAKING PLACE ON THE 10TH FLOORS AS INDICATED PER PLANS FILED HERE WITH. NO CHANGE... | $35,000 | VORNADO OFFICE MANAGEMENT |
| Feb 8, 2021 | 123753063 | Alteration Type II | SIGNED OFF | SPRINKLER MODIFICATIONS TAKING PLACE ON THE 2ND FL AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. | $12,000 | VORNADO OFFICE MANAGEMENT |
| Feb 8, 2021 | 123783343 | Alteration Type II | SIGNED OFF | STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 2ND & 3RD FLOORS AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGR... | $15,000 | VORNADO OFFICE MANAGEMENT |
| Feb 8, 2021 | 123901938 | Alteration Type II | SIGNED OFF | GENERAL CONSTRUCTION, AND MECHANICAL MECHANICAL MODIFICATIONS TAKING PLACE ON THE 15TH FLOORS AS INDICATED PER PLANS ... | $95,000 | VORNADO OFFICE MANAGEMENT |
| Feb 8, 2021 | 123159802 | Alteration Type II | SIGNED OFF | MECHANICAL MODIFICATIONS TAKING PLACE ON THE 2ND FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCU... | $30,000 | VORNADO OFFICE MANAGEMENT |
| Jan 29, 2021 | 123414974 | Alteration Type II | SIGNED OFF | SPRINKLER SYSTEM MODIFICATIONS ON THE CELLAR AND SUB-CELLAR LEVELS WITH RELATED WORK AS PER PLANS SUBMITTED HEREWITH.... | $312,000 | VORNADO OFFICE MANAGEMENT |