770 Broadway • Block 00554 • Lot 0001

380 records

Work filed with the Department of Buildings under its legacy BIS system.

Latest action Job Type Status Work Cost Owner
May 17, 2017 140413942 Alteration Type III SIGNED OFF PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. $0 VORNADO OFFICE MANAGEMENT
May 4, 2017 122886145 Alteration Type II SIGNED OFF MINOR DEMOLITION TAKING PLACE ON THE 14TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. $195,000 VORNADO OFFICE MANAGEMENT
May 4, 2017 121825356 Alteration Type II SIGNED OFF STRUCTURAL CHANGES TO INSTALL WALKWAY AND PIPE RAILING AROUND EXISTING MECHANICAL EQUIPMENT ON ROOF AS INDICATED ON D... $5,000 VORNADO OFFICE MANAGEMENT
May 2, 2017 110428430 Alteration Type II SIGNED OFF PLUMBING WORK ASSOCIATEE WITH INSTALLATION OF BACK FLOW PREVENTER ON SUB CELL AS PER DRAWINGS FILED $115,000 VORNA OFFICE MNGMNT
May 1, 2017 122638253 Alteration Type II SIGNED OFF STRUCTURAL MODIFICATIONS TAKING PLACE RELATED TO SIDEWALK AND VAULT REPAIR AS INDICATED ON THE DRAWINGS. NO CHANGE IN... $257,000 VORNADO OFFICE MANAGEMENT
Apr 19, 2017 122833728 Alteration Type II SIGNED OFF REMOVAL OF SPRINKLER HEADS AND INSTALLATION OF TEMPORARY SPRINKLER LOOP ON THE 9TH FLOOR AS INDICATED ON DRAWINGS. $30,000 VORNADO OFFICE MANAGEMENT
Apr 19, 2017 122905605 Alteration Type II SIGNED OFF SPRINKLER MODIFICATIONS TO TAKE PLACE ON THE 10TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR ... $35,000 VORNADO OFFICE MANAGEMENT LLC
Mar 27, 2017 122899364 Alteration Type II SIGNED OFF GENERAL CONSTRUCTION MODIFICATIONS TO TAKE PLACE ON THE 10TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, ... $520,000 VORNADO OFFICE MANAGEMENT LLC
Mar 23, 2017 122756268 Alteration Type II SIGNED OFF DEMOLITION AND CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 8TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN US... $280,000 VORNADO OFFICE MANAGEMENT
Mar 13, 2017 122132726 Alteration Type II SIGNED OFF MODIFICATION TO EXISTING SPRINKLER SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER TH... $200,000 VORNADO OFFICE MANAGEMENT
Mar 13, 2017 122132717 Alteration Type II SIGNED OFF FILING FOR REMOVAL OF SPRINKLER HEADS AND INSTALLATION OF SPRINKLER TEMP LOOP AS PER PLANS FILED HEREWITH. NO CHANGE ... $95,400 VORNADO OFFICE MANAGEMENT
Feb 14, 2017 122751780 Alteration Type II SIGNED OFF SPRINKLER MODIFICATIONS TAKING PLACE ON THE 8TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUP... $13,500 VORNADO OFFICE MANAGEMENT
Dec 28, 2016 122511022 Alteration Type II SIGNED OFF FIRE ALARM MODIFICATIONS TAKING PLACE ON THE 15TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCC... $110,000 VORNADO OFFICE MANAGEMENT
Dec 14, 2016 122612690 Alteration Type II SIGNED OFF MECHANICAL & PLUMBING MODIFICATIONS TAKING PLACE ON THE 15TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE... $1,944,718 VORNADO OFFICE MANAGEMENT
Dec 6, 2016 121786950 Alteration Type II SIGNED OFF ADDITIONS / MODIFICATIONS TO EXISTING FIRE ALARM SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCC... $114,000 VORNADO OFFICE MANAGEMENT
Nov 28, 2016 122612716 Alteration Type II SIGNED OFF INSTALLATION OF A TEMP SPRINKLER LOOP ON THE 15TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCC... $50,000 VORNADO OFFICE MANAGEMENT
Nov 28, 2016 122501015 Alteration Type II SIGNED OFF RELOCATION OF ONE FIRE HOSE RACK ON THE 15TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. $8,000 VORNADO OFFICE MANAGEMENT
Nov 28, 2016 122612707 Alteration Type II SIGNED OFF SPRINKLER MODIFICATIONS TAKING PLACE ON THE 15TH FLOOR AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCU... $338,575 VORNADO OFFICE MANAGEMENT
Nov 14, 2016 140555389 Alteration Type II SIGNED OFF FILING KITCHEN FIRE SUPPRESSION SYSTEM IN CONJUNCTION WITH JOB#122651549, AS SHOWN ON PLAN. COOKING EQUIPMENT AND COO... $10,000 VORNADO OFFICE MANAGEMENT
Oct 14, 2016 122833719 Alteration Type II SIGNED OFF DEMOLITION OF NON-LOAD BEARING PARTITIONS, REMOVAL OF MECHANICAL DUCTWORK AND REMOVAL OF PLUMBING FIXTURES ON THE 9TH... $315,000 VORNADO OFFICE MANAGEMENT
Oct 4, 2016 122404255 Alteration Type II SIGNED OFF MODIFICATION TO EXISTING SPRINKLER SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER TH... $150,000 VORNADO OFFICE MANAGEMENT
Sep 16, 2016 121766053 Alteration Type II SIGNED OFF MODIFICATION TO EXISTING SPRINKLER SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER T... $10,200 VORNADO OFFICE MANAGEMENT
Sep 13, 2016 122404264 Alteration Type II SIGNED OFF REMOVAL OF SPRINKLER HEADS AND INSTALLATION OF TEMP LOOP AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCC... $75,000 VORNADO OFFICE MANAGEMENT
Aug 24, 2016 122731936 Alteration Type I PERMIT ISSUED - ENTIRE JOB/WORK STRUCTURAL MODIFICATIONS IN ASSOCIATION WITH THE ALT1 TAKING PLACE ON THE 15TH FLOOR AND ROOF. $0 VORNADO OFFICE MANAGEMENT
Aug 16, 2016 121766017 Alteration Type II SIGNED OFF INSTALLATION OF INTERIOR NON LOAD BEARING PARTITIONS AND RELATED FINISHES AS PER PLANS FILED HEREWITH. NO CHANGE IN U... $4,800,000 VORNADO OFFICE MANAGEMENT
Aug 4, 2016 122404273 Alteration Type II SIGNED OFF REMOVAL AND INSTALLATION OF INTERIOR NON LOAD BEARING PARTITIONS AND RELATED FINISHES AS PER PLANS FILED HEREWITH. NO... $4,400,000 VORNADO OFFICE MANAGEMENT
Jun 8, 2016 120506390 Alteration Type II PERMIT ISSUED - ENTIRE JOB/WORK INSTALL TEMPORARY SPRINKLER HEADS ON PART OF FLOOR PER PLANS. $5,000 VORNADO OFFICE MANAGEMENT
Jun 2, 2016 120435984 Alteration Type II PERMIT ISSUED - ENTIRE JOB/WORK SPRINKLER MODIFICATIONS ON THE 10TH AND 11TH FLOOR (J CREW) AS INDICATED ON DRAWINGS. NO CHANGE IN USE EGRESS OR OCCU... $454,000 VORNADO OFFICE MANAGEMENT
Jun 2, 2016 120421953 Alteration Type II PERMIT ISSUED - ENTIRE JOB/WORK STANDPIPE MODIFICATIONS ON THE 10TH FLOOR (J CREW) AS INDICATED ON DRAWINGS. NO CHANGE IN USE EGRESS OR OCCUPANCY. NO... $6,000 VORNADO OFFICE MANAGEMENT
Jun 2, 2016 120910292 Alteration Type II PERMIT ISSUED - ENTIRE JOB/WORK SPRINKLER WORK ON THE 12TH & 13TH FLOOR (J CREW) AS INDICATED ON DRAWINGS. NO CHANGE IN USE EGRESS OR OCCUPANCY. ... $582,800 VORNADO OFFICE MANAGEMENT
May 16, 2016 122742988 Alteration Type III PLAN EXAM - APPROVED FILING FOR SITE SAFETY PLAN APPROVAL ONLY IN CONJUNCTION WITH APPLICATION NUMBER 122751637.NO CHANGES TO USE, OCCUPAN... $1,000 VORNADO OFFICE MANAGEMENT LLC
Apr 20, 2016 122395782 Alteration Type II SIGNED OFF MECHANICAL CHANGES ASSOCIATED WITH REPLACEMENT OF CHILLERS AND RELATED ACCESSORIES ON THE SUB-BASEMENT LEVEL AS PER P... $2,100,000 VORNADO OFFICE MANAGEMENT
Mar 10, 2016 121753156 Alteration Type II SIGNED OFF INTERIOR DEMOLITION ON THE 4TH FLOOR (AOL) ASINDICATED ON DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. $55,000 VORNADO OFFICE MANAGEMENT
Jan 15, 2016 122277794 Alteration Type II SIGNED OFF MINOR DEMOLITION AND CONSTRUCTION WORK TO MODIFY STAIR BULKHEADS AT TWO EGRESS STAIRS (B, G) ON ROOF FOR THE PURPOSE ... $405,400 VORNADO OFFICE MANAGEMENT
Jan 11, 2016 122514056 Alteration Type II SIGNED OFF INTERIOR DEMOLITION OF NONLOADBEARING PARTITIONS ON THE 15TH FLOOR WITH RELATED WORK AS PER PLANS FILED HEREWITH. NO ... $161,575 VORNADO OFFICE MANAGEMENT
Dec 17, 2015 122091869 Alteration Type II SIGNED OFF MODIFICATION OF THE EXISTING CLASS E FIRE ALARM SYSTEMS ON PART OF THE SUBCELLAR LEVEL AS PER PLANS FILED HEREWITH. $9,000 VORNADO OFFICE MANAGEMENT
Sep 30, 2015 122075878 Alteration Type II SIGNED OFF STRUCTURAL WORK FOR SIDEWALK AND VAULT ROOF SLAB REPLACEMENT AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, O... $181,000 VORNADO OFFICE MANAGEMENT
Sep 25, 2015 121774516 Alteration Type II SIGNED OFF MODIFICATION TO EXISTING FIRE ALARM SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER ... $10,000 VORNADO OFFICE MANAGEMENT
Sep 23, 2015 122081709 Alteration Type II SIGNED OFF INTERIOR ARCHITECTURAL CHANGES TO BUILDING MANAGEMENT OFFICE AND PUBLIC CORRIDOR ON PART OF THE SUBCELLAR LEVEL AS PE... $238,700 VORNADO OFFICE MANAGEMENT
Aug 19, 2015 121716606 Alteration Type II SIGNED OFF INSTALLATION OF TEMPORARY LOOP ON THE 8TH FLOOR AS INDICATED ON DRAWINGS $48,000 VORNADO OFFICE MANAGEMENT
Aug 7, 2015 122082398 Alteration Type II SIGNED OFF SPRINKLER SYSTEM MODIFICATIONS TO BUILDING MANAGEMENT OFFICE AND PUBLIC CORRIDOR ON PART OF THE SUBCELLAR LEVEL AS PE... $44,400 VORNADO OFFICE MANAGEMENT
Aug 7, 2015 120871173 Alteration Type II SIGNED OFF REMOVAL OF SPRINKLER HEADS AND INSTALLATION OF TEMPORARY SPRINKLER LOOP ON THE 13TH FLOOR AS INDICATED ON DRAWINGS. $164,500 VORNADO OFFICE MANAGEMENT
Jul 14, 2015 121618302 Alteration Type II SIGNED OFF PLUMBING CHANGES ON THE 4TH, 5TH AND 6TH FLOOR (AOL) AS INDICATED ON DRAWINGS. $45,000 VORNADO OFFICE MANAGEMENT
Jun 16, 2015 122082441 Alteration Type II SIGNED OFF INTERIOR DEMOLITION OF NONLOADBEARING PARTITIONS AND RELATED WORK ON THE 2ND FLOOR AS PER PLANS FILED HEREWITH. NO CH... $74,825 VORNADO OFFICE MANAGEMENT
May 28, 2015 122162159 Alteration Type II SIGNED OFF MODIFICATION TO EXISTING FIRE ALARM SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER T... $150,000 VORNADO OFFICE MANAGEMENT
May 18, 2015 121814787 Alteration Type II SIGNED OFF STRUCTURAL MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. $140,000 VORNADO OFFICE MANAGEMENT
Mar 20, 2015 121675561 Alteration Type II SIGNED OFF PARTITION WORK & INSTALLATION OF DOOR ON THE 15TH FLOOR. NO CHANGE IN OCCUPANCY, USE OR EGRESS. $4,000 VORNADO OFFICE MANAGEMENT
Feb 19, 2015 121680421 Alteration Type II SIGNED OFF INSTALL DEMISING WALL ON THE 7TH FLOOR AS INDICATED ON DRAWINGS. NO CHANGE IN USE EGRESS OR OCCUPANCY. $145,000 VORNADO OFFICE MANAGEMENT
Jan 7, 2015 121766044 Alteration Type II SIGNED OFF REMOVAL AND INSTALLATION OF INTERIOR NON LOAD BEARING PARTITIONS AND RELATED FINISHES AS PER PLANS FILED HEREWITH. NO... $248,672 VORNADO OFFICE MANAGEMENT
Jan 6, 2015 121792015 Alteration Type II SIGNED OFF MODIFICATION TO EXISTING SPRINKLER SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER T... $581,400 VORNADO OFFICE MANAGEMENT